Brady Construction Company contracted to build an apartment complex for a price of $5,000,000.
Construction began in 2013 and was completed in 2015. The following are a series of independent
situations, numbered
through 6, involving differing costs for the project. All costs are stated in thousands of dollars.
Required:
Copy and complete the following table.
Answer:
SUMMARY
Percentage-of-Completion Completed Contract
Situation 2013 2014 2015 2013 2014 2015
1 $166,667 $233,333 $100,000 $0 $0 $500,000
, 2 $166,667 $(66,667) $100,000 $0 $0 $200,000
3 $166,667 $(266,667) $(100,000) $0 $(100,000) $(100,000)
4 $125,000 $375,000 $0 $0 $0 $500,000
5 $125,000 $(125,000) $200,000 $0 $0 $200,000
6 $(100,000) $(100,000) $(100,000) $(100,000) $(100,000) $(100,000)
Situation 1 - Percentage-of-Completion
2013 2014 2015
Contract price $5,000,000 $5,000,000 $5,000,000
Actual costs to date 1,500,000 3,600,000 4,500,000
Estimated costs to complete 3,000,000 900,000 -0-
Total estimated costs 4,500,000 4,500,000 4,500,000
Estimated gross profit
(actual in 2015) $ 500,000 $ 500,000 $ 500,000
Gross profit (loss) recognized:
2013: $1,500,000
= 33.3333% x $500,000 = $166,667
$4,500,000
2014: $3,600,000
= 80.0% x $500,000 = $400,000 – 166,667 = $233,333
$4,500,000