A builder entered into a written contract with a business owner to construct an addition
to the owner's place of business. The builder was to supply all materials for the job, and
was to be paid a total of $200,000. The builder anticipated that his profit would be 10
percent of that amount. Before construction began, the builder received a $25,000
payment from the business owner. The business owner, due to a downturn in his
business, failed to make the first progress payment and ordered the builder to stop
working on the project. At this time, the builder had expended $55,000 and it would
have cost the builder $125,000 to continue the project to completion. The work
completed added $35,000 in value to the building. The builder retained $10,000 of
construction materials purchased but not used in the project, and used them in another
construction job. The builder sued the business owner for breach of contract. What is
maximum amount of damages to which the builder is entitled?
Answers:
A. $20,000
B. $35,000
C. $40,000
D. $55,000 - Answer Answer choice C is correct. The general measure of damages for
the owner's failure to pay the contract price, in whole or in part, is the profits that the
builder would have earned, plus any costs incurred by the builder, less the amount of
any payments made by the owner to the contractor and any materials purchased by the
contractor that are used by the contractor on another job. Here, the builder's profit would
have been $20,000 ($200,000 x 10%) and the builder had expended $55,000 in
constructing the building, for a total of $75,000. (Note: This amount may also be arrived
at by subtracting the cost to complete the building, $125,000, from the contract price,
$200,000.) From this amount is subtracted the payment received by the builder from the
owner ($25,000) and the amount expended by the builder for materials the builder used
on another job ($10,000), leaving $40,000. Answer choice A is incorrect because it
takes into account only the profit that the builder would have earned had the contract
been completed. Answer choice B is incorrect because, while it states one method for
measuring restitutionary damages (i.e., the increase In the value of the owner's building
($35,000)), it fails to take into account the amount paid by the owner to the builder (i.e.,
$25,000). Moreover, the amount is less than the expectancy damages to which the
builder is entitled. Answer choice D is incorrect because, while it states the amount that
the builder expended in reliance on the contract in fails to take into account the value of
the purchased material that he was able to use on another job ($10,000) and also fails
to take into account the amount paid by the owner to the builder (i.e., $25,000).
, A federal act that provided funds to fight HIV/AIDS includes two relevant provisions. The
first provision prohibits the use of funds to promote or advocate the legalization or
practice of prostitution. The second provision requires a recipient of the funds to
expressly adopt and espouse a policy against prostitution. In adopting this act,
Congress specifically found that prostitution was a factor in the spread of HIV/AIDS.
Prior to the adoption of this act, a private organization that received substantial funding
from private sources did not have such a policy because the organization feared that
such a policy would hinder its work with prostitutes, making its programs less effective
in addressing the HIV/AIDS problem. Although the private organization otherwise
qualified as a recipient of federal funds through the act, because the private
organization refused to adopt and espouse the policy against prostitution, the
organization's application for such funds was rejected. The organization has filed an
action in federal court for a declaratory judgment that the act's anti-prostitution policy
requirement violates the organization's First Amendment free speech rights. How should
the court rule?
Answers:
A. For the federal government, because Congress can place conditions on recipients of
federal grants pursuant to the Spending Power of Article I, Section 8 of the U.S.
Constitution.
B. For the federal government, because of the government speech doctrine.
C. For the private organization, because a federal grant cannot be contingent on a
condition that limits a recipient's freedom of speech.
D. For the private organization, because the First Amendment free speech rights
include the right not to be forced by the government to adopt and espouse the
government's views. - Answer Answer choice D is correct. Under the First Amendment,
the government may not tell people what they must believe or say. Here, the
conditioning of a grant on this requirement places an unconstitutional burden on the
organization's exercise of its First Amendment free speech rights. Answer choice A is
incorrect. Congress may place conditions on recipients of federal grants. Generally, if
the recipient finds the conditions offensive, the recipient's option is to refuse the federal
funds. However, Congress may not place conditions on grants that unconstitutionally
burden a recipient's First Amendment rights. Answer choice B is incorrect because the
government speech doctrine does not apply here. This doctrine provides that
government speech is not constrained by the Free Speech Clause of the First
Amendment. The speech subject to constraint here is that of the private organization,
not the government. Answer choice C is incorrect because a grant can be made
contingent on a condition that a recipient refrain from endorsing a particular view.
Congress may even select recipients of federal funds based on whether they hold views
that are consistent with the manner in which those funds are to be used. However,
Congress cannot force a recipient to adopt and espouse a particular view as the
recipient's own view in order to obtain funds the recipient would otherwise be entitled to
receive.