PK0-004 Project+ BEST STUDY GUIDE
2021/2022

A milestone task on the critical path has been completed.

which of the following should the project manager notify?

A owner of predecessor task
B project team
C project sponsor
D project steering committee correct answer- C

During a project assessment, a project manager determines the initial project cost
estimates were incorrect oh, and there is not enough budget left, including reserves, to
complete the project.

Which of the following actions should the project manager take?

A alert the project sponsor of the situation
B contact the customer and request more funding
C announce the project will end due to lack of funds
D attempt to save money in downstream activities correct answer- A

Which of the following is the primary purpose of an MOA or an mou?

A State expectations of all signatory parties to reduce potential misunderstandings

B facilitate potential legal action and resulting remediation if one of the signatory parties
violate any terms

C enumerate a detail code of conduct for all employees, contractors, and
subcontractors participating in the program.

D provide transparency to competitors regarding all signatory parties correct answer- A

two team members have concluded that documentation is not required due to the size
of the current project. The project manager has encouraged them to align strictly with
the process.

which of the following conflict resolution techniques has the project manager utilized?

,A smoothing
B forcing
C compromising
D avoiding correct answer- B

The client accepts the critical design review.

which of the following meetings should be held to move to the next step in the project?

A execution
B kickoff
C closure
D planning correct answer- B

A project manager is working on the project charter.

Which of the following phases does this describe?

A initiation
B planning
C execution
D closing correct answer- A

A project in the execution phase is over budget, and tasks on the critical path are on
schedule.

Which of the following should the project manager do next?

A update the project management plan
B issue a change request
C revise the project charter
D evaluate the impact to the baseline correct answer- D

Several team members report that meeting objectives are not being met.

which of the following documents would a project manager free to make team meetings
more effective? Choose two

1 create an s o w prior to each meeting and adhere to it
2 create a meeting agenda prior to each meeting and adhere to it
3 create a lessons learned list prior to each meeting and adhere to it
4 create a project charter prior to each meeting and adhere to it
5 create an action item list during the meeting and adhere to it
6 create a corrective action plan prior to each meeting and adhere to it
7 create a WBS prior to each meeting and adhere to it

,A 2,5
B 1,4 correct answer- A

Which of the following documents should be used prior to high-level recording to key
stakeholders?

A dashboard
B communication plan
C statement of work
D project charter correct answer- A

A new project charter is being drafted.

which of the following would be the best source for the high-level project requirements?

A sponsor
B project manager
C project management office
D project team correct answer- A

Which of the following project document should be used to record the occurrence of an
unplanned event?

A action log
B risk log
C change log
D issue log correct answer- D

Which of the following documents does offender rely most before committing funding
and resources to a project?

A SOW
B PO
C SLA
D MOU correct answer- A

which of the following measurements would give the project manager the best estimate
of the total cost of an active project?

A EAC
B BAC
C TCPI
D ETC correct answer- A

A customer will have ongoing changes to project requirements.

, which of the following is the best project management methodology for this
requirement?

A waterfall
B agile
C PRINCE2
D BOTTOM UP correct answer- B

Which of the following describes risk mitigation?

A the transfer of the risk to another entity or project inside or outside the organization,
along with the associated costs.

B the understanding of the risks with a detailed explanation and how to project intends
to address the potential for occurrence.

C the quantification of the risk in terms of how much the risk of potentially cost the
project or parent organization.

D The waiting or privatization of the risk against all of their identified risks within this
project or others associated with it. correct answer- B

Which of the following is a definition of an RFP?

A a document sent to potential vendors to solicit a bid for a project.

B a document sent a potential vendors to request information for skills and experience
for a project.

C a document sent to potential vendors to request a commitment for a project.

D a document cents potential vendors to solicit information that excludes pricing
information for a project. correct answer- A

A customer has requested additional features for an active project.

which of the following steps should take place next?

A implement the requested changes
B evaluate the impact of the changes
C update all project documents
D submit the requested changes to the CCB correct answer- B

A project manager has an opportunity to add highly skilled expert to the team who can
increase the probability of the project success.

Written for

Course

Document information

Uploaded on
July 22, 2022
Number of pages
155
Written in
2021/2022
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$11.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
EXAMCOLLECTIVES Herzing University
Follow You need to be logged in order to follow users or courses
Sold
1773
Member since
4 year
Number of followers
1159
Documents
23339
Last sold
2 hours ago
Ace Your Exams with Elite Study Resources | ExamEliteHub on Stuvia

I offer genuine and dependable exam papers that are directly obtained from well-known, reputable institutions as a highly regarded professional who specializes in sourcing study materials. These papers are invaluable resources made to help people who want to become nurses and people who work in other fields prepare for exams. Because of my extensive experience and in-depth knowledge of the subject, I take great care to ensure that each exam paper meets the highest quality, accuracy, and relevance standards, making them an essential component of any successful study plan.

Read more Read less
4.1

446 reviews

5
252
4
57
3
84
2
18
1
35

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions