Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

PMP Earned Value Formulas

Rating
-
Sold
-
Pages
3
Grade
A+
Uploaded on
23-07-2022
Written in
2021/2022

Cost Variance (CV) EV - AC Provides cost performance of the project. Helps determine if the project is proceeding as planned. Negative = over budget = bad Positive = under budget = good" Cost Performance Index (CPI) EV / AC Measure of cost efficiency on a project. Ratio of earned value to actual cost. 1 = good. We are getting $1 for every $1 spent. Funds are used as planned. 1 = good. We are getting $1 for every $1 spent. Funds are used better than planned. 1 = bad. We are getting $1 for every $1 spent. Funds are not used as planned." 00:12 01:15 Schedule Variance (SV) EV - PV Provides schedule performance of the project. Helps determine if the project work is proceeding as planned. Negative = behind schedule = bad Positive = ahead of schedule = good Schedule Performance Index (SPI) EV / PV Measure of schedule efficiency on a project. Ratio of earned value to planned value. Used to determine if a project is behind, on or ahead of schedule. Can be used to help predict when a project will be completed. 1 = good. We are progressing at the originally planned rate. 1 = good. We are progressing at a faster rate than originally planned. 1 = bad. We are progressing at a slower rate than originally planned." Estimate at Completion (EAC) - Same rate of variance BAC / CPI Assumption: use formula if current variances will probably remain the same through the end of the project. This is the formula most often required on the exam. Original budget modified by the cost performance. The result is a monetary value." Estimate at Completion (EAC) - New Estimate AC + Bottom-up ETC Assumption: use formula if original estimate was fundamentally flawed or conditions have changed and invalidated original estimating assumptions. Actual Cost plus a new estimate for the remaining work. Result is a monetary value." Estimate at Completion (EAC) - Onetime Variance AC + (BAC - EV) Assumption: use formula if current variances will probably not occur again through the end of the project, which means the original budget is more reliable.Actual cost to date (AC) plus unearned budget (BAC - EV). Result is a monetary value." Estimate at Completion (EAC) - Meet Deadline EAC = AC + [(BAC - EV) / (CPI * SPI)] Assumption: use formula if project is over budget but still needs to meet a schedule deadline. Actual cost to date (AC) plus unearned budget (BAC - EV) modified by both cost performance and schedule performance. Result is a monetary value. Estimate to Complete (ETC) ETC = EAC - AC Expected total cost minus actual cost to date. Result is a monetary value that will tell us how much more the project will cost. Inversion of the same formula from the EAC calculations. Note: This ETC formula is listed in only one (the "most famous") PMP prep workbook. No others list it. We recommend using it, if no keywords are given." Estimate to Complete (ETC) - New Estimate ETC = Bottom-up ETC This is not the result of a calculation or formula, but simply a new estimate of the remaining cost. We create a new estimate when it is thought that the original estimate was flawed. Estimate to Complete (ETC) - Onetime Variance BAC - EV (BAC - EV) will give the unearned project budget. Result is a monetary value. Assumption: use formula if current variances will probably not occur again through the end of the project, which means the original budget is more reliable Estimate to Complete (ETC) - Meet Deadline (BAC - EV) / (CPI * SPI) The remaining unearned budget (BAC - EV) modified by both cost performance and schedule performance. Result is a monetary value. Assumption: use formula if project is over budget but still needs to meet a schedule deadline."

Show more Read less
Institution
Course

Content preview

PMP Earned Value Formulas
Cost Variance (CV) - Answer EV - AC
Provides cost performance of the project. Helps determine if the project is proceeding
as planned.
Negative = over budget = bad Positive = under budget = good"

Cost Performance Index (CPI) - Answer EV / AC
Measure of cost efficiency on a project. Ratio of earned value to actual cost.
1 = good. We are getting $1 for every $1 spent. Funds are used as planned.
>1 = good. We are getting >$1 for every $1 spent. Funds are used better than planned.
<1 = bad. We are getting <$1 for every $1 spent. Funds are not used as planned."

Schedule Variance (SV) - Answer EV - PV
Provides schedule performance of the project. Helps determine if the project work is
proceeding as planned. Negative = behind schedule = bad Positive = ahead of schedule
= good

Schedule Performance Index (SPI) - Answer EV / PV
Measure of schedule efficiency on a project. Ratio of earned value to planned value.
Used to determine if a project is behind, on or ahead of schedule. Can be used to help
predict when a project will be completed.
1 = good. We are progressing at the originally planned rate.
>1 = good. We are progressing at a faster rate than originally planned.
<1 = bad. We are progressing at a slower rate than originally planned."

Estimate at Completion (EAC) - Same rate of variance - Answer BAC / CPI
Assumption: use formula if current variances will probably remain the same through the
end of the project. This is the formula most often required on the exam.
Original budget modified by the cost performance. The result is a monetary value."

Estimate at Completion (EAC) - New Estimate - Answer AC + Bottom-up ETC
Assumption: use formula if original estimate was fundamentally flawed or conditions
have changed and invalidated original estimating assumptions.
Actual Cost plus a new estimate for the remaining work. Result is a monetary value."

Estimate at Completion (EAC) - Onetime Variance - Answer AC + (BAC - EV)
Assumption: use formula if current variances will probably not occur again through the
end of the project, which means the original budget is more reliable.Actual cost to date
(AC) plus unearned budget (BAC - EV). Result is a monetary value."

Estimate at Completion (EAC) - Meet Deadline - Answer EAC = AC + [(BAC - EV) / (CPI
* SPI)]
Assumption: use formula if project is over budget but still needs to meet a schedule
deadline.

Written for

Course

Document information

Uploaded on
July 23, 2022
Number of pages
3
Written in
2021/2022
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$10.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
EvaTee Phoenix University
Follow You need to be logged in order to follow users or courses
Sold
5202
Member since
4 year
Number of followers
3567
Documents
55582
Last sold
5 hours ago
TIGHT DEADLINE? I CAN HELP

Many students don\'t have the time to work on their academic papers due to balancing with other responsibilities, for example, part-time work. I can relate. kindly don\'t hesitate to contact me, my study guides, notes and exams or test banks, are 100% graded

3.8

947 reviews

5
451
4
167
3
171
2
48
1
110

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions