Question 1
Which of the following are relevant project documents you should link to in your project
plan? Select all that apply.
point
RACI charts that define roles and responsibilities for individuals on a team
Correct
The project charter that defines the project and outlines project goal details
Correct
The organization chart that depicts everyone who works in the company with their
contact information
Daily review emails and messages between the stakeholders, project manager, and
project team
2.
Question 2
Fill in the blank: Time estimation predicts the total amount of time required to complete a
task, while the actual time it takes to complete a task _____.
point
may vary depending on overlooked potential risks
is not relevant
shouldn’t change
depends on stakeholder input
Incorrect
Please review the video on estimating time.
, 3.
Question 3
A project manager is leading an initiative that includes changing an organization's logo
and slogan. What mandatory tasks should be part of the critical path? Select all that
apply.
0. point
Determine a new slogan
Set a budget
Correct
Get employees to respond positively in a survey
This should not be selected
Please review the video on capacity planning and critical path.
Receive sponsor approval
4.
Question 4
Which of the following scenarios exemplify how a project manager can use interpersonal
skills? Select all that apply.
0. point
The web designer on your project tells you that they’re not sure they can meet the
deadline for all the mock up pages. You ask the designer some questions about the
project, such as what amount of time they need for each page mock so you can help
prioritize what is feasible.
The timeline is set for the Office Green project. You tell the web designer on Wednesday
that you’ll need a complete mock up for the site by Friday.
This should not be selected
Please review the video on getting accurate estimates from your team.