10164011 6
Service life
Source of funding streams
Expected operational use
Technology will be sufficiently mature when needed.
2) Which DoD policy document details the Milestone decision process, statutory and
regulatory acquisition document requirements, and acquisition management responsibilities?
10163984 1
DoD Instruction 5000.73
DoD Instruction 5000.02
DoD Directive 5000.01
None of the above.
3) _________________________________ consists of production, military construction, and
deployment costs.
10163989 1
Investment
Operating and Support
Research and Development
Disposal
4) In respect to the Cost Analysis Requirements Description (CARD) preparation, which of the
following is correct (select three)?
10164005 6
The CARD should make liberal references to other program documents.
The CARD’s narrative section should be approximately 20 pages in length, excluding
tables.
This study source was downloaded by 100000790716548 from CourseHero.com on 08-18-2022 15:43:46 GMT -05:00
https://www.coursehero.com/file/32513468/MOD-1-2-EXAMdocx/
, The CARD is prepared by the CAPE.
The CARD`s tables amplify the narrative to provide the minimum essential information
necessary to support the preparation of life-cycle cost estimates.
5) _______________________________ assesses potential materiel solutions that could
satisfy validated capability requirements documented in the Initial Capabilities Document
(ICD) and supports a decision in the most cost effective solution.
10163987 1
Analysis of Alternatives
Affordability Analysis
Business Case Analysis
Economic Analysis
6) A Work Breakdown Structure is a _______________ family tree composed of hardware,
software, services, data, and facilities resulting from systems engineering efforts during the
acquisition of a defense materiel item.
10164003 1
Product-oriented
All of these are correct
None of these are correct
Functionally-oriented
7) When a _________________ creates a life cycle cost estimate, it is in the form of a
Component Cost Estimate.
10163991 1
Program Office
Service Cost Agency
Cost Assessment and Program Evaluation (CAPE)
Office of Management and Budget (OMB)
8) During this step of the cost estimation process the suitability of a specific approach will
depend to a large degree on the maturity of the program and the level of detail of the available