Development QUESTIONS AND ANSWERS
Using the Standard Capability Maturity Model Integration Appraisal Method for
Process Improvement (SCAMPI), an organization whose acquisition processes are
well documented and standardized would be rated at least: Correct Answer: -Level
1
-Level 2
-*Level 3*
-Level 4
When selecting a software developer, which of the following should contractors
possess (Select all that apply)? Correct Answer: -*Successful past performance
record*
-*Domain experience in developing comparable software systems*
-Maturity level four
-*Demonstrable mature software development capability and processes*
With regard to exceptions to the full funding policy, _________ funds are
budgeted as a separate procurement line item from the related end item. Correct
Answer: -Multiyear Procurement
-Incremental
-*Advance Procurement*
-Low Rate Initial Production (LRIP)
Earned value management (EVM) reports are available to help the program
manager (PM) track the contractor's cost, schedule, and performance against a
Performance Measurement Baseline. Correct Answer: -*True*
-False
In the Planning, Programming, Budgeting and Execution (PPBE) process, one
result of the programming activities is the __________ Correct Answer: -Future
Years Development Program (FYDP)
-Budget Estimate Submission (BES)
-Defense Planning Guidance (DPG)
-*Program Objectives Memorandum (POM)*