A program manager should normally look for opportunities to integrate
developmental testing (DT) and operational testing (OT) in order to save time and
money. Correct Answer: -*True*
-False
Program cost increases and schedules slips are most likely caused by
__________________, changes to the design, and changes to the production
processes. Correct Answer: -Changes to the number of systems ordered
-Robust and accurate configuration management
-Well-defined and documented technical data packages
-*Changes to user capability needs*
An Early Operational Assessment is typically conducted to
_____________________. Correct Answer: -Support the decision to begin low
rate initial production (LRIP)
-Meet the requirement to conduct initial operational test and evaluation (IOT&E)
-Track the evolution of critical technical parameters against the system design
-*Identify potential operational effectiveness and suitability issues during system
development*
The management of internal interface design would usually be the responsibility of
the _____________? Correct Answer: -Independent Test and Evaluation Agency
-Joint Interoperability Test Command
-Government Program Manager
-*Contractor*
The Program Manager just received approval of his proposed acquisition strategy
with one exception: he has been directed to make maximum use of existing Air
Force software. Which of the best software acquisition practices is most applicable
to his situation? Correct Answer: -Use metrics to manage
-Use system based software design
-*Assess reuse risks and cost*
-Inspect requirements and design