Milestone 2
All correct
answers 1
Which of the following is the first step in creating a WBS?
Identify all activities needed for the project
Verify that the work has been properly sequenced
Refer to the scope to identify the deliverable
Identify all tasks needed to make the work
manageable CONCEPT
Creating a WBS
2
Which of the following is correct about gaining approval for a project plan?
The schedule cannot be adjusted.
The plan is accepted as is.
Most projects require formal stakeholder approval.
Before it can be approved, the plan must be established as the baseline for the
project. CONCEPT
Gaining Approval
3
Which of the following does NOT affect a time estimate?
Equipment availability
Effort estimates
Schedule dependencies
Communication requirements
CONCEPT
Time and Effort
Estimates 4
Allen needs to know about actions related to a project he is associated with, however, he is not asked to
provide advice and he has no decision-making authority.
Which of the following RACI elements is assigned to Allen?
Responsible
Consulted
, Informed
Accountable
CONCEPT
Responsibility Matrix
5
Which of the following individuals listed in the RACI performs the project work?
Informed
Accountable
Consulted
Responsible
CONCEPT
Responsibility Matrix
6
What of the following information is NOT included in the risk register for a project?
Date risk recorded
Classification of risk
Description of risk
Impact to project budget
CONCEPT
Classifying and Recording
Risks 7
Which of the following is the longest string of dependent project activities required to complete a
project in the shortest amount of time?
Effort estimate
Resource estimate
Critical path
Project schedule
CONCEPT
Project Schedule
8
Which of the following components of a project plan is completed first?
Work breakdown structure