Summary Chapter 15 'managing the schedule' Gower Handbook of Project Management, ISBN: 9781472422965

Beoordeling
-
Verkocht
-
Pagina's
5
Geüpload op
07-10-2022
Geschreven in
2022/2023

Chapter 10 Gower Handbook of Project Management, ISBN: 2965

Instelling
Vak

Voorbeeld van de inhoud

Summary of the hand of project management | Remco van der Schoot


- Developing a more comprehensive understanding of each stakeholders needs, interests and
expectations, regardless of the potential harm or help to the project

Stakeholder management process consists of three sub processes: stakeholder analysis, stakeholder engagement
and disengagement.

2.3. HOOFDSTUK 15 – MANAGING THE SCHEDULE (P.233-247)
Project management = the implementation arm of strategic management, used for implementing any change,
whether hard or soft.
Operations management = about managing day to day operations of the organization


2.3.1. PROJECT PLANNING AND SCHEDULING: DATA AND TERMINOLOGY
Activity name or code = used to identify the activity easily.
- Could be used for sorting and filtering activities into categories

Activity description = describes the content and context of the activity and what is supposed to be done
- Could also include acceptance criteria, quality standards and specification

Activity sequence (precedence relationship, logic, order of operation) = specifies which activities need to be done
before starting the next.

Network diagram (ND) = a pictorial presentation of the sequence in which the activities are logically needed to
be done to deliver the project
- Do not incorporate any resource constraints in the network diagram

Activity resources requirement estimate = identify all the resources needed to do the activities and estimate the
amount need for each.

Activity duration estimate = an estimate is calculated through the resource intensity and time.
- Resource intensity = the number of each resource used per time period.
- Effort = the total required number of man-days/hours needed to complete a task measured in units such
as engineer-hours, managers-days and analyst-months
o Amount of workers*time need on the activity
▪ Two people work on a job for three weeks -> 2x3x5 = 30 man-days

Activity cost estimate = once we have decided on the planned duration of the task which is a function of resource
intensity and Volume of Work (VOW) and the productivity of the resources, we are in a position to estimate the
costs and to start scheduling of the project.

Earliest Start (ES) = the earliest time an activity could start given all the work that has to take place before it.
Earliest Finish (EF): is the earliest time an activity could finish.
Latest Finish (LF): is the latest time an activity could finish given all the work that has to be done after it.
Latest Start (LS): is the latest time an activity could start.

Total Float/Slack (TF): is the amount of time an activity could be delayed without delaying the completion of the
project.
Free Float/Slack (FF): is the amount of time an activity could be delayed without delaying any other activity.

Critical Activity: is an activity with no slack/float. Delaying a critical activity will delay the completion of the
project.


P a g i n a 15 | 35

, Summary of the hand of project management | Remco van der Schoot


Critical Path: is the longest path in the project network and the minimum possible time to finish the project. It
consists of a sequence of critical activities linking the start of the project to its end.


2.3.2. WHAT IT TAKES TO SCHEDULE A PROJECT
Important function of planning and scheduling = to provide a time, cost, quality and scope control tool for
effective and efficient implementation of project management (coordination and integration of all efforts for
optimum execution of the project).

1. Planning = about data collection and intelligence gathering, organizing thoughts, making decisions about how
we want to do the project (know what is going to be done). Consists of the following steps:
- Developing the scope documents
- Developing WBS
- Developing the list of activities
- Collecting and developing data for all the activities
- Developing the network diagram
- Developing all the assumptions and constraints needed for scheduling

2. Scheduling = focused on time, resources and costs (developing a blueprint (baseline) for execution of the
project). Fixing the position of each activity on the time axis that is deciding when to start and finish each activity.
Consists of the following steps:
- Time only analysis (scheduling the project ignoring resource constraints)
- Resource based schedule analysis
- Cost analysis and budget assessment
- Optimal schedule development (integrates time, cost, quality and scope into the schedule)

3. The end product = al baseline schedule which will be used for monitoring and control of the project, directing
the project to successful delivery of the end product and closing the project.
- Planning and scheduling processes are flexible and dynamic

DEVELOPING SCOPE DOCUMENT, WBS AND LIST OF ACTIVITIES
1. Initiating a project and developing a project brief
a. Later more details are added in preparation of the request for proposal (RFP), and
b. Even more details are added during the development of project initiation documents or in the
process of getting the final version of the scope approved

Formal scope document
Best practice for minimizing changes during the project: formal scope document agreed on by all the stakeholders
to be used for planning and scheduling of the project and encompasses:
- The boundary of the project
- Major deliverable
- Main functionalities expected from the system or project
- What is part of the system and what is not

WBS.
The formal scope document is the basis for the work breakdown structure (WBS) and encompasses the method
used to explicitly address and account for all the elements which must be delivered. Ways to develop a WBS
(based on the logic of breakdown):
- Project lifecycle/chronology
- Phases of a project
- Geographical/location of parts or zones
- Functions
- Etc.

P a g i n a 16 | 35

Gekoppeld boek

Geschreven voor

Instelling
Studie
Vak

Documentinformatie

Heel boek samengevat?
Onbekend
Geüpload op
7 oktober 2022
Aantal pagina's
5
Geschreven in
2022/2023
Type
SAMENVATTING

Onderwerpen

$4.79
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
RSCHO Hogeschool Utrecht
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
305
Lid sinds
3 jaar
Aantal volgers
135
Documenten
58
Laatst verkocht
1 maand geleden
De studeerkast

De studeerkast bevat mijn voorbereidende documenten, welke ik heb gebruik tijdens mijn vijf jaar () aan de Hogeschool Utrecht (HU). In deze vijf jaar heb ik de bachelor Integrale Veiligheidskunde (IVK) en de master Projectmanagement (MPM) afgerond. De studeerkast wordt komende vier jaar aangevuld met samenvatting op het gebied cybersecurity, zoals CISSP, CISM en The Computer Security Handbook. Ik schrijf samenvatting vaak uitgebreider en maak veel gebruik van tabellen, bullet-points en figuren. Als je iets tegenkomt waar ik kan verbeteren of iets wat fout staat aangegeven. Bericht me s.v.p. dan ga ik hiermee direct aan de slag!

Lees meer Lees minder
4.3

26 beoordelingen

5
11
4
13
3
2
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen