answers. Latest update. Graded A
Cost Variance formula - ✔✔Earned Value (EV) - Actual Cost (AC)
What are the 6 constraints? - ✔✔Scope, Risk, Resources, Quality, Schedule, Budget
Initiating (Process Group) - ✔✔Processes performed to define a new PROJECT or a new PHASE of an
existing project
Planning (Process Group) - ✔✔Processes performed to establish total scope of effort, define and refine
objectives, and develop a course of action to attain the objectives
Executing (Process Group) - ✔✔Processes performed to complete the work defined in the project
management plan to satisfy objectives
Monitoring & Controlling (Process Group) - ✔✔Processes to track, review, and orchestrate progress and
performance of a project
How many processes are in EXECUTING? - ✔✔8
How many processes are in PLANNING? - ✔✔24
How many processes are in INITIATING? - ✔✔2
How many processes are in CLOSING? - ✔✔2
How many processes are in MONITORING & CONTROLLING? - ✔✔11
,What are INPUTS? - ✔✔Tools and Techniques you can use to DO the process
What are OUTPUTS? - ✔✔One or more things you can GET as a RESULT of doing the process
How many processes are there? - ✔✔47
How many knowledge areas are there? - ✔✔10
What are the 10 knowledge areas? - ✔✔Integration, Scope, Time, Cost, Quality, Human Resources,
Communication, Risk, Procurement, Stakeholder
Closing (Process Group) - ✔✔Processes to conclude all activities across all process groups of a project
Validate Scope: What process group? What knowledge area? - ✔✔Monitoring & Controlling (PG)
Scope Management (KA)
Validate Scope: What Tools and Techniques? - ✔✔Inspection
Group Decision Making
Develop Project Charter: What process group? What knowledge area? - ✔✔Initiating (PG)
Integration Management (KA)
Develop Project Charter: What Tools and Techniques? - ✔✔Expert Judgement
Facilitation Techniques
Create WBS: What process group? What knowledge area? - ✔✔Planning (PG)
Scope Management (KA)
, Create WBS: What Tools and Techniques? - ✔✔Decomposition
Expert Judgement
Plan Scope Management: What process group? What knowledge area? - ✔✔Planning (PG)
Scope Management (KA)
Plan Scope Management: What Tools and Techniques? - ✔✔Expert Judgement
Meetings
Direct & Manage Project Work: What process group? What knowledge area? - ✔✔Executing (PG)
Integration Management (KA)
Direct & Manage Project Work: What Tools and Techniques? - ✔✔Expert Judgement
PMIS
Meetings
Monitor & Control Project Work: What process group? What knowledge area? - ✔✔Monitoring and
Controlling (PG)
Integration Management (KA)
Monitor & Control Project Work: What Tools and Techniques? - ✔✔Expert Judgement
Analytical Techniques
PMIS
Meetings
Perform Integrated Change Control: What process group? What knowledge area? - ✔✔Monitoring and
Controlling (PG)
Integration Management (KA)