Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CAPM Practice Exam - Quiz with COMPLETE SOLUTION | 150 Questions with 100% Correct Answers

Beoordeling
-
Verkocht
-
Pagina's
19
Cijfer
A+
Geüpload op
04-11-2022
Geschreven in
2022/2023

Mandatory and discretionary - - What other dependency types are possible in a project apart from internal and external dependencies? All of the above - - Which of the below can be the reasons for raising and processing a change request? A Corrective and preventive actions B Updates to controlled documents (like baselines and plans) and deliverables C Defect fixes D All of the above Perform qualitative risk analysis - - In which process are risks prioritized for further analysis or action by assessing their probability, impact and other characteristics? Knowledge management and information management - - Identify the two techniques which are unique to the Manage Knowledge process? Project-oriented - - In what organizational structure type is the project manager's role full time? Product analysis - - When defining project scope, techniques like systems/value engineering and analysis are used. These are collectively known as:

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

CAPM Practice Exam - Quiz with COMPLETE SOLUTION | 150
Questions with 100% Correct Answers
What other dependency types are possible in a project apart from internal and external
dependencies? Correct Answer: Mandatory and discretionary

Which of the below can be the reasons for raising and processing a change request?
A Corrective and preventive actions
B Updates to controlled documents (like baselines and plans) and deliverables
C Defect fixes
D All of the above Correct Answer: All of the above

In which process are risks prioritized for further analysis or action by assessing their probability,
impact and other characteristics? Correct Answer: Perform qualitative risk analysis

Identify the two techniques which are unique to the Manage Knowledge process? Correct
Answer: Knowledge management and information management

In what organizational structure type is the project manager's role full time? Correct Answer:
Project-oriented

When defining project scope, techniques like systems/value engineering and analysis are used.
These are collectively known as: Correct Answer: Product analysis

Procurement documents, procurement strategy, bid documents, procurement SOW, source
selection criteria, make-or-buy decisions and independent cost estimates are outputs of which
process? Correct Answer: Plan procurement management

Prioritization and allocation of resources in an organization is an objective of: Correct Answer:
Portfolio management

Which of the below describes the 100% rule of WBS?
A The WBS should include all the project and product work
B The WBS should not include any work which is not part of the project or product work
CA&B
D None of the above Correct Answer: C

Stakeholder analysis technique is used in which process for the first time? Correct Answer:
Identify Stakeholders

There are two outputs from the Plan Scope Management process. One of them is Scope
Management Plan. Which is the other one? Correct Answer: Requirements management plan

An activity is most likely expected to take 7 days. The maximum duration is expected to be 10
days and the minimum 5 days. Calculate the expected duration for this activity. Correct Answer:
7.16 days

,Which risk response strategies are used only to respond to threats? Correct Answer: Avoid,
mitigate

The three factors namely management elements, governance frameworks and organizational
structures which interact and determine the power, influence, interests, competence and political
capabilities of the people in an organization, are together known as: Correct Answer: An
organizational system

An output of the Monitor and Control Project Work process is: Correct Answer: Work
performance report

Which of the below is not one of the three skills listed for a project manager as per PMI Talent
Triangle®? Correct Answer: Technology management

In the Manage Communications process, project information is collected and distributed as per
the format and level of detail desired by stakeholders. What is the name of this technique?
Correct Answer: Project reporting

In which process group a new project or phase is defined and authorization is given to start it?
Correct Answer: Initiating

A project has activities A,B,C,D and E with durations 3,5,7,2 and 4 days respectively. A and B
are started together. When A and B both are completed, C and E are started together. When C
finishes, D is performed. When B is completed, E is performed. When both D and E are done,
the project is completed. What is the total float for activity E? Correct Answer: 5 days

Two of the resource optimization techniques are: Correct Answer: Resource levelling and
resource smoothing

In general, who focuses on systems and structure and who on relationships with people? Correct
Answer: Manager and leader respectively

Funding limit reconciliation is a technique in which process? Correct Answer: Determine budget

What-if scenario analysis and simulation are techniques under which process of project schedule
management? Correct Answer: Develop schedule, control schedule

Which of the following will not be described in the scope management plan? Correct Answer:
Detailed project and product scope

Reviewing changes between desired and current stakeholder engagement levels, and adjusting
communications as necessary is best done by which technique in the Control Communications
process? Correct Answer: Stakeholder Engagement Assessment Matrix

, Just-in-time (JIT) manufacturing, Kaizen, total productive maintenance (TPM) , lean
management are trends and practices in which knowledge area of project management? Correct
Answer: resource management

Which of the below is correct about the cost baseline? Correct Answer: It is an output of the
Determine Budget process and includes the contingency reserve

In which of the following organizational structure types is the project manager's authority
weakest? Correct Answer: Functional

Which of the below statement(s) is/are correct with respect to the Validate Scope process?
Correct Answer: Verified deliverables are inputs, accepted deliverables are outputs

Which of the below is an input of the Close Project or Phase process? Correct Answer:
Accepted deliverables

Which of the below accuracy ranges is applicable for a definitive cost estimate? Correct Answer:
-5% to +10%

In which process is the stakeholder register created? Correct Answer: Identify Stakeholders

Quantitative risk analysis includes a few complex techniques. Which of the below lists these
techniques?
A Decision tree analysis and influence diagrams
B Representations of uncertainty, simulation and sensitivity analysis
CA&B
D Probability and impact matrix, risk hierarchical chart Correct Answer: C

Another name for cause and effect diagram is: (there may be more than one)
A Fish bone diagram
B Ishikawa diagram
C Why-why diagram
D All of the above Correct Answer: D

Which costing approach is used in agile projects? Correct Answer: Initially a high level forecast
and later detailed estimates for short term planning horizons

Which of the below is/are correct about organizational project management?
A Value is realized in operations
B Value decisions are made by portfolios
C Results are delivered by projects and programs
D All of the above Correct Answer: D

One of the two key outputs of the Identify Risks process is the risk register. Which is the other
one? Correct Answer: Risk Report

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
4 november 2022
Aantal pagina's
19
Geschreven in
2022/2023
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$10.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF


Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Classroom NURSING
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
4881
Lid sinds
4 jaar
Aantal volgers
3232
Documenten
55436
Laatst verkocht
22 uur geleden
NURSING

Assignments, Case Studies, Research, Essay writing service, Questions and Answers, Discussions etc. for students who want to see results twice as fast. I have done papers of various topics and complexities. I am punctual and always submit work on-deadline. I write engaging and informative content on all subjects. Send me your research papers, case studies, psychology papers, etc, and I’ll do them to the best of my abilities. Writing is my passion when it comes to academic work. I’ve got a good sense of structure and enjoy finding interesting ways to deliver information in any given paper. I love impressing clients with my work, and I am very punctual about deadlines. Send me your assignment and I’ll take it to the next level. I strive for my content to be of the highest quality. Your wishes come first— send me your requirements and I’ll make a piece of work with fresh ideas, consistent structure, and following the academic formatting rules. For every student you refer to me with an order that is completed and paid transparently, I will do one assignment for you, free of charge!!!!!!!!!!!!

Lees meer Lees minder
4.0

1192 beoordelingen

5
631
4
216
3
196
2
40
1
109

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen