with Complete Solution
The project manager and team should consider each process along with its inputs, tools and
outputs. As a result, they should choose which are applicable. This effort is known as Correct
Answer: Tailoring
In Initiating, a project charter is created. According to the PMBOK, which person or group may
help write the charter? Correct Answer: Project management team
The Monitoring and Controlling Process Group involves: Correct Answer: Tracking, reviewing,
and orchestrating the progress of the project
Much information is collected and distributed during the life of the project. Data that is collected
form controlling processes and analyzed in context is called: Correct Answer: Work
performance information
The project manager should perform the Initiating processes at the start of each phase in order to:
Correct Answer: Keep the project focused on the business need
As Planning occurs, more and more is known about the project and the project management plan
becomes increasingly detailed. This detailing is known specifically as: Correct Answer:
Progressive elaboration
The process group that involves coordinating people and resources, managing stakeholder
expectations and completing the work defined in the project management plan is known as:
Correct Answer: Executing
The Process group that contains more than 50% of the processes is known as: Correct Answer:
Planning
>Direct and Manage Project Work is the process of leading and performing the work defined in
the project management plan. There are several outputs from this process. The only one defined
as typically tangible components completed to meet the project objectives is: Correct Answer:
Deliverables
In conjunction with the project manager, which person or group needs to address every process
and the project environment to determine the level of implementation for each process? Correct
Answer: Project team
The key benefit of one of the Integration processes is that it allows stakeholders to understand
the current state of the project, the steps taken, budget, schedule, and scope forecasts. This
process is known as: Correct Answer: Monitor and Control Project Work