Cost Variance formula Correct Answer: Earned Value (EV) - Actual Cost (AC)
What are the 6 constraints? Correct Answer: Scope, Risk, Resources, Quality, Schedule, Budget
Initiating (Process Group) Correct Answer: Processes performed to define a new PROJECT or a
new PHASE of an existing project
Planning (Process Group) Correct Answer: Processes performed to establish total scope of
effort, define and refine objectives, and develop a course of action to attain the objectives
Executing (Process Group) Correct Answer: Processes performed to complete the work defined
in the project management plan to satisfy objectives
Monitoring & Controlling (Process Group) Correct Answer: Processes to track, review, and
orchestrate progress and performance of a project
How many processes are in EXECUTING? Correct Answer: 8
How many processes are in PLANNING? Correct Answer: 24
How many processes are in INITIATING? Correct Answer: 2
How many processes are in CLOSING? Correct Answer: 2
How many processes are in MONITORING & CONTROLLING? Correct Answer: 11
What are INPUTS? Correct Answer: Tools and Techniques you can use to DO the process
What are OUTPUTS? Correct Answer: One or more things you can GET as a RESULT of doing
the process
How many processes are there? Correct Answer: 47
How many knowledge areas are there? Correct Answer: 10
What are the 10 knowledge areas? Correct Answer: Integration, Scope, Time, Cost, Quality,
Human Resources, Communication, Risk, Procurement, Stakeholder
Closing (Process Group) Correct Answer: Processes to conclude all activities across all process
groups of a project
Validate Scope: What process group? What knowledge area? Correct Answer: Monitoring &
Controlling (PG)
Scope Management (KA)
, Validate Scope: What Tools and Techniques? Correct Answer: Inspection
Group Decision Making
Develop Project Charter: What process group? What knowledge area? Correct Answer:
Initiating (PG)
Integration Management (KA)
Develop Project Charter: What Tools and Techniques? Correct Answer: Expert Judgement
Facilitation Techniques
Create WBS: What process group? What knowledge area? Correct Answer: Planning (PG)
Scope Management (KA)
Create WBS: What Tools and Techniques? Correct Answer: Decomposition
Expert Judgement
Plan Scope Management: What process group? What knowledge area? Correct Answer:
Planning (PG)
Scope Management (KA)
Plan Scope Management: What Tools and Techniques? Correct Answer: Expert Judgement
Meetings
Direct & Manage Project Work: What process group? What knowledge area? Correct Answer:
Executing (PG)
Integration Management (KA)
Direct & Manage Project Work: What Tools and Techniques? Correct Answer: Expert
Judgement
PMIS
Meetings
Monitor & Control Project Work: What process group? What knowledge area? Correct Answer:
Monitoring and Controlling (PG)
Integration Management (KA)
Monitor & Control Project Work: What Tools and Techniques? Correct Answer: Expert
Judgement
Analytical Techniques
PMIS
Meetings
Perform Integrated Change Control: What process group? What knowledge area? Correct
Answer: Monitoring and Controlling (PG)
Integration Management (KA)