C722 Pre-Assessment – Project Management (PHEO) 1. A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project. Which aspect of project management applies to this firm’s project? YOUR ANSW ER CORRE CT ANSW ER Independent operations Interdependent tasks Regulatory concept External environment 2. A firm begins its strategic business initiative of developing a new business model to enhance its competitiveness. What can be identified as a strategic business initiative for this firm? YOUR ANSW ER CORRE CT ANSW ER Timely payment of liabilities Liaison with regulatory agencies Improvement in product design Environmental scanning 3. A firm begins a strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. Which stakeholder would have triggered this strategic business initiative? YOUR ANSW ER CORRE CT ANSW ER Director of operations Production supervisor

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

C722 Pre-Assessment – Project
Management (PHEO)
1.
A firm begins its strategic business initiative of developing a new business model that will
allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the
firm initiates a business management project.

Which aspect of project management applies to this firm’s project?


CORRE
YOUR
CT
ANSW
ANSW
ER
ER

Independent operations

Interdependent tasks

Regulatory concept

External environment


2. A firm begins its strategic business initiative of developing a new business model to
enhance its competitiveness.

What can be identified as a strategic business initiative for this firm?

CORRE
YOUR
CT
ANSW
ANSW
ER
ER

Timely payment of liabilities


Liaison with regulatory agencies

Improvement in product design

Environmental scanning


3. A firm begins a strategic business initiative of developing a new business model that will
allow the firm to deliver an efficient, tailored service to its customers.

Which stakeholder would have triggered this strategic business initiative?

YOUR CORRE
ANSW CT
ER ANSW
ER

Director of operations


Production supervisor

Project sponsor

, YOUR CORRE
ANSW CT
ER ANSW
ER

Financial controller

,Project Management and the Project Manager

4. Which group is included in the five process groups?

CORRE
YOUR
CT
ANSW
ANSW
ER
ER

Risk process group

Closing process group

Communication process group

Quality process group


5. What does PRINCE2 stand
for?
CORRE
YOUR
CT
ANSW
ANSW
ER
ER

PRoject INsights for CompEtitiveness

PRojects IN a Competitive Environment

PRoject INsights and CompEtencies

PRojects IN a Controlled Environment


6. Which PMBOK process group is described as the delivery part of project management
where the main activity happens?
CORRE
YOUR
CT
ANSW
ANSW
ER
ER

Planning

Executing

Controlling

Closing

, Organizational Structures

7. Which advantage does the functional (departmentalized) organizational structure provide
for a firm with multiple projects?
CORRE
YOUR
CT
ANSW
ANSW
ER
ER

Lines of authority are clear.

The project customer is the only focus.

It is efficient for collaboration and cooperation between departments.

Each project is managed holistically.


8. Which two organizations are examples of organizations with the functional organizational
structure?

Choose 2 answers


CORRE
YOUR
CT
ANSW
ANSW
ER
ER

Microsoft

The U.S. Department of State

The U.S. National Aeronautics and Space Administration (NASA)

The U.S Department of Energy

Google Inc.


9. An organization expects to use a project management office (PMO) to support multiple
projects that will be implemented within a projectized organizational structure.

Which implied effect is a benefit to this organization?

CORRE
YOUR
CT
ANSW
ANSW
ER
ER

Project team members retain their functional responsibilities.

Project team members become full-time employees.

Project team members gain access to the newest technologies and skill
sets.

Geschreven voor

Vak

Documentinformatie

Geüpload op
10 januari 2023
Aantal pagina's
43
Geschreven in
2022/2023
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$14.48
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
LECTMAGGY Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
146
Lid sinds
3 jaar
Aantal volgers
121
Documenten
6314
Laatst verkocht
2 weken geleden
LECTMAGGY

Here, you will find everything you need in NURSING EXAMS AND TESTBANKS.Contact us, to fetch it for you in minutes if we do not have it in this shop.BUY WITHOUT DOUBT!!!!Always leave a review after purchasing any document so as to make sure our customers are 100% satisfied.

3.3

28 beoordelingen

5
8
4
3
3
11
2
0
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen