MGMT 404 Test 1 and 2 ,2023 with 100%correct questions and answers
We have a project (Cardinal), with these activities in days: Activity A with duration 4 and no precedents. Activity B with duration 15 and predecessor. A, Activity C with duration 9 and predecessor. A, Activity D with duration 2 and predecessor B, Activity E has duration 6 and predecessors B and C, Activity F has duration 4 and predecessor D, and Activity G has duration 15 and predecessors of E and F. Draw this to answer the following questions. How long is this project scheduled to take? 40 Days From question #1, what is the EF for Node E? 25 From question #1, what is the LF for Node E? 25 What is the critical path from #1? A~B~E~G From question #1, what is the EF for Node D? 21 From question #1, what is the ES for Node E? 19 From question #1, what is the LS for Node C? 10 From question #1, what is the slack in node E? 0 Day(s) From question #1, what is the LF for Node D? 21 From question #1, what is the slack in node D? 0 day(s) From question #1, what is the ES for Node C? 4 From historical data, we know it takes 45 minutes to paint a 100 square foot area. We have to paint a 800 square foot area. How long should we put for the duration of this activity? 360 minutes
Written for
- Institution
- MGMT 404
- Course
- MGMT 404
Document information
- Uploaded on
- February 6, 2023
- Number of pages
- 7
- Written in
- 2022/2023
- Type
- Exam (elaborations)
- Contains
- Questions & answers
Subjects
-
mgmt 404 test 1 and 2
-
2023 with 100correct questions and answers
-
we have a project cardinal
-
with these activities in days activity a with duration 4 and no precedents activity b with duration 1