Operations Management (GMS401) Quiz 1 Latest 2023 with complete solution Activities on the critical path of a project have ______ slack. Select one: a. positive b. zero c. free d. negative zero Activity slack time for an activity in a project means the activity has fell behind schedule. Select one: a. True b. False False Adding resources to reduce the amount of time it takes to complete project activities is called: Select one: a. crashing b. scope creep c. simulation d. indirect project costs crashing A diagram representing project activities including arrows and nodes to indicate sequential relations among activities is called a: Select one: a. Gantt chart b. Precedence network diagram c. Work breakdown structure d. Bar chart Precedence network diagram A major limitation of using Gantt charts for project management is that they do not: Select one: a. Indicate all the major activities involved. b. Indicate the closeout phase. c. Show the timing of activities. d. Show relationships among activities. Show relationships among activities. Ensuring that project activities are defined as work packages that can be completed by a specific worker or team is an essential part of what aspect of project planning? Select one: a. Defining project scope b. Risk management planning c. Work breakdown structure d. Project scheduling

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

Operations Management (GMS401) Quiz 1 Latest 2023
with complete solution
Activities on the critical path of a project have ______ slack.
Select one:
a. positive
b. zero
c. free
d. negative
zero
Activity slack time for an activity in a project means the activity has fell behind schedule.
Select one:
a. True
b. False
False
Adding resources to reduce the amount of time it takes to complete project activities is
called:
Select one:
a. crashing
b. scope creep
c. simulation
d. indirect project costs
crashing
A diagram representing project activities including arrows and nodes to indicate
sequential relations among activities is called a:
Select one:
a. Gantt chart
b. Precedence network diagram
c. Work breakdown structure
d. Bar chart
Precedence network diagram
A major limitation of using Gantt charts for project management is that they do not:
Select one:
a. Indicate all the major activities involved.
b. Indicate the closeout phase.
c. Show the timing of activities.
d. Show relationships among activities.
Show relationships among activities.
Ensuring that project activities are defined as work packages that can be completed by
a specific worker or team is an essential part of what aspect of project planning?
Select one:
a. Defining project scope
b. Risk management planning
c. Work breakdown structure
d. Project scheduling

, Work breakdown structure
For the probabilistic approach to precedence network analysis, the duration of project
activities is estimated based on:
Select one:
a. The average of the optimistic, most likely and pessimistic estimates
b. An unequal weighted average of the optimistic, most likely and pessimistic estimates
c. Most likely + pessimistic - optimistic estimates
d. None of these calculations
An unequal weighted average of the optimistic, most likely and pessimistic estimates
Gantt charts cannot be used for managing projects because they do not indicate
relationships among activities.
a. True
b. False
False
Near the beginning of a project, risk occurrence has a relatively high probability, but the
cost associated with risk events early in a project tends to be low.
Select one:
a. True
b. False
True
Project control involves assessing progress against plans and:
Select one:
a. Developing revised project schedules.
b. Taking corrective action if necessary.
c. Reallocating slack among activities.
d. Revising project budgets.
Taking corrective action if necessary.
Project execution refers to the decision project managers sometimes have to make to
cancel a project.
Select one:
a. True
b. False
False
Project management software enables more "what if" scenario planning.
Select one:
a. True
b. False
True
Projects go through a life cycle that involves initiation, planning and scheduling,
execution, control and closeout.
Select one:
a. True
b. False
True
Reducing the length of a project, "crashing", by increasing direct costs to speed up
activities may be done to realize savings in indirect costs such as equipment or project

Geschreven voor

Vak

Documentinformatie

Geüpload op
29 maart 2023
Aantal pagina's
12
Geschreven in
2022/2023
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$10.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
LECTMAGGY Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
146
Lid sinds
3 jaar
Aantal volgers
121
Documenten
6311
Laatst verkocht
1 week geleden
LECTMAGGY

Here, you will find everything you need in NURSING EXAMS AND TESTBANKS.Contact us, to fetch it for you in minutes if we do not have it in this shop.BUY WITHOUT DOUBT!!!!Always leave a review after purchasing any document so as to make sure our customers are 100% satisfied.

3.3

28 beoordelingen

5
8
4
3
3
11
2
0
1
6

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen