Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

WEEK 6 QUIZ (MY ANSWERS).

Beoordeling
-
Verkocht
-
Pagina's
7
Cijfer
A+
Geüpload op
07-04-2023
Geschreven in
2022/2023

WEEK 6 QUIZ (MY ANSWERS).

Instelling
Vak

Voorbeeld van de inhoud

PROJ 592 – WEEK 6 – QUIZ 2
(CO E) Using the network below and the additional information provided, find
Question 1
(a) the crash cost per day per activity;
(b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and
20
(c) what the extra cost is to crash the project.

Activity Normal Crash Time Normal Cost Crash Cost
Time
A 5 3 $300 $350
B 3 2 $250 $325
C 6 4 $400 $700
D 5 3 $150 $200



MY ANSWER

(a) Crash Cost Per day Per Activity:

Crash Cost = (Crash Cost - Normal Cost) / (Normal Time - Crash Time)

Activity A = ($350-$300) / (5-3)

= $50/2

Activity A = $25

Activity B = ($325-$250) / (3-2)

= $75/1

Activity B = $75

Activity C = ($700-$400) / (6-4)

= $300/2

Activity C = $150

Activity D = ($200-$150) / (5-3)

= $50/2

Activity D = $25

(b) Which activities should be crashed to meet a project deadline of 12 days at minimum cost?

First, we need to consider the project's Critical Path which is:




This study source was downloaded by 100000861168648 from CourseHero.com on 04-07-2023 02:24:12 GMT -05:00


https://www.coursehero.com/file/52418147/WEEK-6-QUIZ-MY-ANSWERSdocx/

, B-C-D = 3-6-5 = 2 days

and the project's Normal Completion Time which is: (c) what the extra cost is to crash the project
which is: B+C+D = 3+6+5 = 14 days

In this project, Activity D has the lowest crash cost. Therefore, we can crash it by 2 days to
meet the project's deadline of 12 days at minimum cost

(c) what the extra cost is to crash the project?

Extra Cost = Daily Cost for Activity D x Critical Path

= $25 x 2

Extra Cost to Crash Project = $50
(CO E) The following information is extracted from a project to develop a state-of-the-art alternative power energy
Question 2
storage device. 20 pts
Activity Duration Predecessors Resources
A 4 days -- 1 research engineer
B 3 days A 1 test engineer
C 5 days A 1 design engineer
D 2 days A 1 marketing specialist
E 3 days B 1 prototype builder
F 4 days D 1 test engineer
The owner has stipulated that in order to provide continuity throughout the project, the same individual must
handle all activities under his or her discipline. Activities on this project cannot be split.

a. Identify any resource conflicts in the above project. State the activities involved, the timeframe of the
conflict(s), which resources are involved, and the quantity required.
b. Given the owner's stipulation regarding project continuity and the need to minimize project duration,
how can this conflict be resolved? What will be the effect on the project duration?


A. Identify any resource conflicts in the above project. State the activities involved,
the timeframe of the conflict(s), which resources are involved, and the quantity
required.

• The resource conflict in this project is between Activity B and Activity F.
• Activity B would still be ongoing at Day 7 of the project while Activity F is expected
to begin.
• Both activities require 1 Test Engineer during overlapping time periods.

B. Given the owner's stipulation regarding project continuity and the need to minimize
project duration, how can this conflict be resolved? What will be the effect on the project
duration?

Conflict Resolution: Schedule Activity B as a predecessor of Activity F instead and start it on
Day 8.



This study source was downloaded by 100000861168648 from CourseHero.com on 04-07-2023 02:24:12 GMT -05:00


https://www.coursehero.com/file/52418147/WEEK-6-QUIZ-MY-ANSWERSdocx/

Geschreven voor

Vak

Documentinformatie

Geüpload op
7 april 2023
Aantal pagina's
7
Geschreven in
2022/2023
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$8.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
faithnzuna

Maak kennis met de verkoper

Seller avatar
faithnzuna Uon
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1
Lid sinds
3 jaar
Aantal volgers
1
Documenten
492
Laatst verkocht
2 jaar geleden

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen