What are Joint Acquisition Programs? - Answer Joint Acquisition Programs is any acqusition system, subsystem, component, or technology program with astrategy that includes funding by more than one DoD component during any phase of a system's life cycle. Who decides to place programs under joint acquisition management? - Answer The MDA decides whether to place programs under joint management and designates the lead executive DoD component. What law requires an analysis of potential opportunities of international cooperation? - Answer 10 USC 2350a(e) requires international cooperation consideration in the initial aquisition strategy for a program. When international programs may be established in the defense acqusition program - Answer Decision to include international partners needs to be included during development of the initial capabilities document but no early than the material and solution analysis phase. When is Earned Value Management (EVM) implemented - Answer EVM is part of program management . It ensures that cost , schedule and technical aspects of the contract are truly integrated. In what type of contracts EVM is required - Answer EVM is required on Cost, and/or Incentive contracts valued at greater than $20M. What is EVM? - Answer Earned Value Management is a tool that 1. Relates the scope of the work to its associated budgets and schedule. 2. Measures the work progress in objective terms 3. States that value of the work completed in dollars and other measurable units. What are EVM techniques? - Answer Correlate the budgeted cost of worked scheduled with the budget cost of work performed (BCWP) 1. 0/100 Earned Value Technique 2. Percent Start/Percent Finish EV Technique (50/50) (25/75) (80/20) 3. Percent Complete 4. Units Completed 5. Equivalent Units Describe the Percent Start/Percent Finish EV Technique - Answer Is an objective earned value technique tied to the start and completion of a work package task, often referred to % assigned to the start and finish milestone such as (50/50...) Thsi technique tends to overstate performance in the first half of the period of performance and uderstate performance in the last half. What is the most important step in EVM system? - Answer Is the establishment of the Performance Measurement Baseline (PMB)or the Budgeted Cost of Work Schedule (BCWS) What is the PMB in and EVM? - Answer The PMB includes the undistributed budget, all summary level planning package budgets, and all control account budgets. It does not include management reserve. What is the final step of the PMB? - Answer Is to classify work, to allocate the budget and to time phase the control account work package budgets. This last phase is calculate BWCS How do we classify work packages in EVM? - Answer in 3 categories, Discrete, apportioned effort, and level of effort. Describe the realignment of the PMB - Answer Rebaselining, Replanning, and Reprogramming What is Reprogramming? - Answer Reprogramming is a comprehensive realignment of the remaining performance measurement baseline that results in a total budget and/or total schedule that exceeds the contractual requirements. It is the process that results in an Over-Target Baseline or OTB and an Over-Target Schedule OTS. Schedule Performance Index (SPI) formula - Answer SPI=BCWP/BCWS

Show more Read less
Institution
Course

Content preview

CDFM Module 4 Graded To Pass
What are Joint Acquisition Programs? - Answer Joint Acquisition Programs is any
acqusition system, subsystem, component, or technology program with astrategy
that includes funding by more than one DoD component during any phase of a
system's life cycle.

Who decides to place programs under joint acquisition management? - Answer The
MDA decides whether to place programs under joint management and designates
the lead executive DoD component.

What law requires an analysis of potential opportunities of international cooperation?
- Answer 10 USC 2350a(e) requires international cooperation consideration in the
initial aquisition strategy for a program.

When international programs may be established in the defense acqusition program
- Answer Decision to include international partners needs to be included during
development of the initial capabilities document but no early than the material and
solution analysis phase.

When is Earned Value Management (EVM) implemented - Answer EVM is part of
program management . It ensures that cost , schedule and technical aspects of the
contract are truly integrated.

In what type of contracts EVM is required - Answer EVM is required on Cost, and/or
Incentive contracts valued at greater than $20M.

What is EVM? - Answer Earned Value Management is a tool that
1. Relates the scope of the work to its associated budgets and schedule.
2. Measures the work progress in objective terms
3. States that value of the work completed in dollars and other measurable units.

What are EVM techniques? - Answer Correlate the budgeted cost of worked
scheduled with the budget cost of work performed (BCWP)
1. 0/100 Earned Value Technique
2. Percent Start/Percent Finish EV Technique (50/50) (25/75) (80/20)
3. Percent Complete
4. Units Completed
5. Equivalent Units

Describe the Percent Start/Percent Finish EV Technique - Answer Is an objective
earned value technique tied to the start and completion of a work package task,
often referred to % assigned to the start and finish milestone such as (50/50...)
Thsi technique tends to overstate performance in the first half of the period of
performance and uderstate performance in the last half.

What is the most important step in EVM system? - Answer Is the establishment of
the Performance Measurement Baseline (PMB)or the Budgeted Cost of Work
Schedule (BCWS)

, CDFM Module 4 Graded To Pass
What is the PMB in and EVM? - Answer The PMB includes the undistributed budget,
all summary level planning package budgets, and all control account budgets. It
does not include management reserve.

What is the final step of the PMB? - Answer Is to classify work, to allocate the budget
and to time phase the control account work package budgets. This last phase is
calculate BWCS

How do we classify work packages in EVM? - Answer in 3 categories, Discrete,
apportioned effort, and level of effort.

Describe the realignment of the PMB - Answer Rebaselining, Replanning, and
Reprogramming

What is Reprogramming? - Answer Reprogramming is a comprehensive realignment
of the remaining performance measurement baseline that results in a total budget
and/or total schedule that exceeds the contractual requirements. It is the process
that results in an Over-Target Baseline or OTB and an Over-Target Schedule OTS.

Schedule Performance Index (SPI) formula - Answer SPI=BCWP/BCWS

Estimate at Completion (EAC) formula - Answer
EAC=ACWP+[(BAC-BCWP)/(Performance Factor)]

EAC Compsite formula - Answer ACWPcum+[(BAC-BCWPcum)/(CPIcum*SPIcum)]
Upper Value (worst case)

EVM Terminology - Answer EAC=Estimate at Completion
BAC=Budget at Completion(current)
BCWS=Budget Cost of Work Scheduled (current)
BWCP=Budget Cost of Work Performed (earned value)
ACWP=Actual Cost of Work Performed

What is the Contractor Cost and Software Data Reporting (CSDR) - Answer The
CSDR system involves two formal contractor reports, the COntractor Cost Data
Report (CCDR) and the Software Resources Data Report (SRDR)

What is Contract Performance Report (CPR) - Answer The PM should obtain from
the contractor a CPR (DD form 2734) on all contracts the meet or exceed EVMS
dollar thresholds and require EVMS compliance. The CPR provides contract cost
and schedule performance for program mangement.

What is Contract Funds Status Report (CFSR) - Answer (DD 1586) has no specific
application thresholds but PMs should evaluate contracts of less than $1.3M. FFP
contracts should not apply the CFSR unless unusual circumnstances dictate funding
visibility.

What is Government Contract Quality Assurance (GCQA) - Answer DCMA Q&A
personnel conducts quality assurance as identified in contract administration
delegations by the KO.

Written for

Course

Document information

Uploaded on
July 5, 2023
Number of pages
14
Written in
2022/2023
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$6.99
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
PROFICIENTTUTOR

Get to know the seller

Seller avatar
PROFICIENTTUTOR New York University
Follow You need to be logged in order to follow users or courses
Sold
1
Member since
2 year
Number of followers
0
Documents
577
Last sold
1 year ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions