GFEBS Project Systems Course Questions and Answers (2022/2023) 1. What is a project definition?: The project definition contains data used for the entire project. It contains default values which can be passed on to the WBS elements, or influence them, such as: Project Profile Project Control values (e.g., user status profile) Organizational data Planning parameters Settlement Rules Unique Project Number The Project Profile is often called the "DNA" of a PS project; it determines many attributes of the project. The Project Profile cannot be changed after project creation. 2. What is a Project Definition? (2 of 2): In the project definition, default values are maintained for a project, such as the settlement rule, Person Responsible, or Plant. The default values can then be copied for a new WBS elements created for this project. The default values will be copied into new WBS elements created for the project, but may be changed with the exception of Project Profile. 3. What is a Work Breakdown Structure?: The WBS forms the basis for all subsequent planning tasks in the project. The emphasis is placed on: Planning Description Funding and Availability Control Costs and Fund Consumption Reporting Monitoring of costs, basic dates, and the statuses 4. Work Breakdown Structure (WBS): In a WBS, the groupings of work are described in the project as individual elements in a hierarchy. The work is broken down in the project, step-by-step, until the level of detail is reached necessary to carry it out. These groupings of works are WBS Elements. So in GFEBS, a Work Breakdown Structure is a hierarchical arrangement of WBS elements under a project definition. In GFEBS, there can only be one WBS directly below the Project Definition. This is known as the Level 1 WBS, and will have the same number (and usually name) as the Project Definition. 5. WBS Elements: WBS elements are arranged hierarchically so that the most atomic work that can be described and funded with a single LOA (line of account- ing) are at the bottom. Typically, execution (accrual of expenses) only occurs at this lowest level, though that does not have to be the case. Since the WBS is structured hierarchically, we're able to summarize and display the data for the corresponding higher-level WBS elements, or all the way up to the Project Definition level. Click on the note icon below for more information 6. WBS Elements - Operative Indicators: GFEBS uses Operative Indicators to define characteristics that control functionality of a WBS - they define whether a given WBS can or cannot be used in some very important processes. Click on each image for each process. Click on the note icon for more information. 7. Planning Element: WBS's that can have planned costs entered against them must be marked by checking the Planning Element operative indicator. 8. Account Assignment Element: WBS's that can have actual costs accrued (executed) against them must be marked by checking the Account Assignment Element Operative Indicator. 9. Billing Element: WBS's that can be referenced on a Sales order for a reim- bursable must be marked by checking the Billing Element Operative Indicator. 10. Which of the following is used to define the characteristics of a WBS element?: Operative Indicators 11. A good project structures supports which of the following?: Cost Report- ing Funding / Funded Program Design Execution All of the above 12. True or False: In PS, the terms "Project" and "Project Definition" are synonymous: False 13. True or False: A WBS element can have multiple lines of accounting (LOA).: False 14. Project Systems Text and Documents: PS text and documents are objects that can be assigned to WBS elements. PS text are user-definable texts that are managed in a PS text catalog. The texts are classified into different text types. You can assign one or more WBS elements to PS text. Also, External documents in various formats (Excel, Word, PPT, BMP, and CAD) can be assigned to WBS elements. 15. Project Template: It is often convenient to create one project from another to avoid having to re-create the entire structure manually and re-enter all the data. This is especially true if you have many projects that are similar to one another, or if you are "rolling over" a project from one fiscal year to the next. You can create a project by copying from either a template (Standard Project) or a regular working project (known "Copying Operative.") Note that the term "template" is often used loosely to indicate either a standard project or an operative project whose purpose is to be a template. Copying Projects using either method is not described here in further detail - there are Job Aids and OLHP's that describe the processes. Click on the images for each type of project. Click on the note icon for more information. 16. Standard Projects: By using Templates (called "Standard Projects" in PS) which you create with transaction CJ91 as the source for creating a new operative project. 17. Operative Project: By copying one normal project (known as an "Operative Project") to another. This can be accomplished entirely within CJ20N. 18. Designing a Project - Objectives: Before we can discuss Project Structure, we must first ask the question, "What is the purpose of a Project Structure?" A clear and unambiguous project structure must form the basis for its planning, funding, reporting, monitoring, control, and successful execution. 19. Reporting: is the structure clear and detailed enough to produce meaningful cost reports without being overly complex and burdensome? In general, a structure which will support proper reporting will also support execution (Cost Collection) well. 20. Planning: Is the structure sufficient to make both high-level and detailed cost plans if necessary? 21. Funding: does the structure support the funding for the project? Keep in mind that a single WBS can only have a single Line of Accounting (LOA). 22. Project Structure: There are additional practical considerations concerning cost collection / execution and reporting. For instance, we could technically build a project structure that looks like this like the graphic (assuming we only had one source of funding). However, your command leadership would have no idea how expensive various components or phases of the project were. All execution would simply be posted against the single WBS. This is known as "building to the funding structure" and is NOT a best practice in GFEBS.

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

GFEBS Project Systems Course
Questions and Answers (2022/2023)


1. What is a project definition?: The project definition contains data
used for the entire project. It contains default values which can be
passed on to the WBS elements, or influence them, such as:


Project Profile
Project Control values (e.g., user status
profile) Organizational data
Planning
parameters
Settlement Rules
Unique Project
Number


The Project Profile is often called the "DNA" of a PS project; it
determines many attributes of the project. The Project Profile cannot
be changed after project creation.

2. What is a Project Definition? (2 of 2): In the project definition, default
values are maintained for a project, such as the settlement rule,
Person Responsible, or Plant. The default values can then be copied for
1/

,a new WBS elements created for this project.


The default values will be copied into new WBS elements created for
the project, but may be changed with the exception of Project Profile.

3. What is a Work Breakdown Structure?: The WBS forms the basis
for all subsequent planning tasks in the project.


The emphasis is placed on:


Planning
Descriptio
n
Funding and Availability Control
Costs and Fund Consumption Reporting
Monitoring of costs, basic dates, and the
statuses

4. Work Breakdown Structure (WBS): In a WBS, the groupings of work
are described in the project as individual elements in a hierarchy. The
work is broken down in the project, step-by-step, until the level of
detail is reached necessary to carry it out. These groupings of works
are WBS Elements.


So in GFEBS, a Work Breakdown Structure is a hierarchical
arrangement of WBS elements under a project definition.


2/

,In GFEBS, there can only be one WBS directly below the Project
Definition. This is known as the Level 1 WBS, and will have the same
number (and usually name) as the Project Definition.

5. WBS Elements: WBS elements are arranged hierarchically so that the
most atomic work that can be described and funded with a single LOA
(line of account- ing) are at the bottom. Typically, execution (accrual of
expenses) only occurs at this lowest level, though that does not have
to be the case.


Since the WBS is structured hierarchically, we're able to summarize
and display the data for the corresponding higher-level WBS elements,
or all the way up to the Project Definition level.


Click on the note icon below for more information

6. WBS Elements - Operative Indicators: GFEBS uses Operative
Indicators to define characteristics that control functionality of a WBS
- they define whether a given WBS can or cannot be used in some
very important processes.


Click on each image for each
process. Click on the note icon for
more information.

7. Planning Element: WBS's that can have planned costs entered
against them must be marked by checking the Planning Element
3/

, operative indicator.

8. Account Assignment Element: WBS's that can have actual costs
accrued (executed) against them must be marked by checking the
Account Assignment Element Operative Indicator.

9. Billing Element: WBS's that can be referenced on a Sales order for
a reim- bursable must be marked by checking the Billing Element
Operative Indicator.

10.Which of the following is used to define the characteristics of a
WBS element?: Operative Indicators

11.A good project structures supports which of the following?: Cost
Report- ing
Funding / Funded Program
Design Execution
All of the above

12.True or False: In PS, the terms "Project" and "Project Definition"
are synonymous: False




4/

Geschreven voor

Vak

Documentinformatie

Geüpload op
7 juli 2023
Aantal pagina's
33
Geschreven in
2022/2023
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$7.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
PROFICIENTTUTOR

Maak kennis met de verkoper

Seller avatar
PROFICIENTTUTOR New York University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
1
Lid sinds
2 jaar
Aantal volgers
0
Documenten
577
Laatst verkocht
1 jaar geleden

0.0

0 beoordelingen

5
0
4
0
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen