Which provide a standard format for displaying project schedule information by listing project activities
and their corresponding start and finish dates in a calendar format?
a. PERT analysis
b. Arrow diagramming method
c. Critical path analysis
d. Gantt charts
How does critical chain scheduling protect tasks on the critical chain from being delayed?
a. fast tracking
b. feeding buffers
c. dummy activities
d. critical paths
In an AOA network diagram, what occurs when two or more activities follow a single node?
a. buffers
b. combinations
c. mergers
d. bursts
In project schedule management, which process generates the main outputs of an activity list, activity
attributes, and a milestone list?
a. estimating activity durations
b. defining activities
c. resource estimating activities
d. sequencing activities
The technique of fast tracking can result in lengthening the project schedule.
True
False
, Which is a similarity between the crashing and fast tracking?
a. both are network diagramming techniques used primarily to predict total project
duration
b. both spread out tasks over a long period of time to ensure the quality of work is
maintained
c. both can shorten the time needed to finish a project
d. both invariably result in increases in total project costs
Which technique involves network diagramming and is used primarily to predict total project duration?
a. resource breakdown structure
b. arrow diagramming method
c. Gantt chart
d. critical path analysis
Which is an output of schedule control?
a. resource requirements
b. milestones lists
c. activity attributes
d. change requests
In project schedule management, what is the next step after defining project activities?
a. controlling the schedule
b. determining their dependencies
c. planning schedule management
d. estimating activity duration
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
True
False
and their corresponding start and finish dates in a calendar format?
a. PERT analysis
b. Arrow diagramming method
c. Critical path analysis
d. Gantt charts
How does critical chain scheduling protect tasks on the critical chain from being delayed?
a. fast tracking
b. feeding buffers
c. dummy activities
d. critical paths
In an AOA network diagram, what occurs when two or more activities follow a single node?
a. buffers
b. combinations
c. mergers
d. bursts
In project schedule management, which process generates the main outputs of an activity list, activity
attributes, and a milestone list?
a. estimating activity durations
b. defining activities
c. resource estimating activities
d. sequencing activities
The technique of fast tracking can result in lengthening the project schedule.
True
False
, Which is a similarity between the crashing and fast tracking?
a. both are network diagramming techniques used primarily to predict total project
duration
b. both spread out tasks over a long period of time to ensure the quality of work is
maintained
c. both can shorten the time needed to finish a project
d. both invariably result in increases in total project costs
Which technique involves network diagramming and is used primarily to predict total project duration?
a. resource breakdown structure
b. arrow diagramming method
c. Gantt chart
d. critical path analysis
Which is an output of schedule control?
a. resource requirements
b. milestones lists
c. activity attributes
d. change requests
In project schedule management, what is the next step after defining project activities?
a. controlling the schedule
b. determining their dependencies
c. planning schedule management
d. estimating activity duration
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
True
False