SOFTWARE ENGINEERING 1 PRELIM EXAM FALL 2023
WITH COMPLETE SOLUTION
Question 1
Correct
Mark 1.00 out of 1.00
Flag question
Question text
is probably the most important phase for long-term support as
well as for the reputation of the company.
Select one:
a. Coding
b. Maintenance
c. Testing
d. Planning
Feedback
Your answer is correct.
Question 2
Correct
Mark 1.00 out of 1.00
Flag question
Question text
These are systems that collect data from their environment using a set of
sensors and send that data to other systems for processing.
Select one:
a. Systems for modeling and simulation.
b. Systems of systems
c. Data collection systems
d. Entertainment system
Feedback
,SOFTWARE ENGINEERING 1 PRELIM EXAM FALL 2023
WITH COMPLETE SOLUTION
Your answer is correct.
Question 3
Correct
Mark 1.00 out of 1.00
Flag question
Question text
It is a very basic check to see if all software components compile with each
other without a problem.
Select one:
a. Regression or Stress Testing
b. Sanity Testing
c. Functional Testing
d. Unit Testing
Feedback
Your answer is correct.
Question 4
Incorrect
Mark 1.00 out of 1.00
Flag question
Question text
Which of these does not affect different types of software as a whole?
Select one:
a. Heterogeneity
b. Security
c. Business and social change
d. Flexibility
Feedback
, SOFTWARE ENGINEERING 1 PRELIM EXAM FALL 2023
WITH COMPLETE SOLUTION
Your answer is correct.
Question 5
Correct
Mark 1.00 out of 1.00
Flag question
Question text
The fundamental notions of software engineering does not account for ?
Select one:
a. Software processes
b. Software Security
c. Software Validation
d. Software reuse
Feedback
Your answer is correct.
Question 6
Correct
Mark 1.00 out of 1.00
Flag question
Question text
Which of these software engineering activities are not a part of software
processes ?
Select one:
a. Software specification
b. Software development
c. Software validation
d. Software dependence
Feedback
WITH COMPLETE SOLUTION
Question 1
Correct
Mark 1.00 out of 1.00
Flag question
Question text
is probably the most important phase for long-term support as
well as for the reputation of the company.
Select one:
a. Coding
b. Maintenance
c. Testing
d. Planning
Feedback
Your answer is correct.
Question 2
Correct
Mark 1.00 out of 1.00
Flag question
Question text
These are systems that collect data from their environment using a set of
sensors and send that data to other systems for processing.
Select one:
a. Systems for modeling and simulation.
b. Systems of systems
c. Data collection systems
d. Entertainment system
Feedback
,SOFTWARE ENGINEERING 1 PRELIM EXAM FALL 2023
WITH COMPLETE SOLUTION
Your answer is correct.
Question 3
Correct
Mark 1.00 out of 1.00
Flag question
Question text
It is a very basic check to see if all software components compile with each
other without a problem.
Select one:
a. Regression or Stress Testing
b. Sanity Testing
c. Functional Testing
d. Unit Testing
Feedback
Your answer is correct.
Question 4
Incorrect
Mark 1.00 out of 1.00
Flag question
Question text
Which of these does not affect different types of software as a whole?
Select one:
a. Heterogeneity
b. Security
c. Business and social change
d. Flexibility
Feedback
, SOFTWARE ENGINEERING 1 PRELIM EXAM FALL 2023
WITH COMPLETE SOLUTION
Your answer is correct.
Question 5
Correct
Mark 1.00 out of 1.00
Flag question
Question text
The fundamental notions of software engineering does not account for ?
Select one:
a. Software processes
b. Software Security
c. Software Validation
d. Software reuse
Feedback
Your answer is correct.
Question 6
Correct
Mark 1.00 out of 1.00
Flag question
Question text
Which of these software engineering activities are not a part of software
processes ?
Select one:
a. Software specification
b. Software development
c. Software validation
d. Software dependence
Feedback