Pass
what would be the volume of a room that measures 7 meters long by 6 meters wide and 3 meters
high ✔✔126 meters = 7*6*3
What would a mechanical drawing be used for? ✔✔location of heating , plumbing and
ventilation in a venue
How is the volume of a space calculated ✔✔Length times width times hight
What is the most important in formation to be gathered on a site visit ✔✔room size and layout
When conducting a site visit if a ladder is needed what type of ladder should be used and why?
✔✔fiberglass or wood in case a surface might be electrified
A scale drawing unit of 1/1:20 signifies what type of scale-drawing measurement? ✔✔a
common metric scale
, When considering customer constraints for ___, the signal type, distance from viewers, aspect
ratio and source resolution are all limiting factors. ✔✔image display
When documenting requirements for network services, a formal technical document called a(n)
_______ is often utilized. ✔✔SLA( service level agreement)
One major difference between the Service Level Agreement process and the traditional Program
Report is the SLA focuses upon ✔✔Measurement of service through monitoring procedures
"When gathering and documenting site information and requirements for the overall functional
needs of an AV system, a document called the _____ is usually produced." ✔✔program report
"When gathering and documenting site information and requirements for the overall functional
needs of an AV system, a document called the _____ is usually produced." ✔✔" Take pictures
for reference and note any potential conflicts or obstructions"
"When collecting information during a site survey, it is good practice to do which of the
following?" ✔✔"Take pictures for reference and note any potential conflicts or obstructions"