GANTT CHART FOR PLANNING DORMTORY CONSTRUCTION NAME: Jamie Burke
Phase of Construction Start Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
plans drawn up by an architect 1
site cleared 4
ground work and base layed 5
utilities installed 6
scaffolding set up 9
brickwork built to roof level 11
roof trusses up and covered 13
first fix joinery 14
first fix eletrics 17
catch up 19
plaster walls 21
second fix joinery 24
second fix electrics 27
Fix solar panels to roof 28
Decorate 32
clean site 37
make snagging list 39 6
hand over domitory to school
40
Phase of Construction Start Duration 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51
plans drawn up by an architect 1
site cleared 4
ground work and base layed 5
utilities installed 6
scaffolding set up 9
brickwork built to roof level 11
roof trusses up and covered 13
first fix joinery 14
first fix eletrics 17
catch up 19
plaster walls 21
second fix joinery 24
second fix electrics 27
Fix solar panels to roof 28
Decorate 32
clean site 37
make snagging list 39 6
hand over domitory to school
40