The "triple constraint" of project management includes the controlling and
management of:
Schedule, cost, and scope
The following are all project management process groups:
--Initiating
--Executing
--Monitoring
Which of the following is critical for ensuring project success?
Organizational commitment
Who has input to project initiation?
Stakeholders
Project requirements must be all of the following:
--Clear
--Measurable
--Prioritized
The following is the official written acknowledgement and recognition that a
project exists?
The Project Charter
A WBS is:
Is based on the scope statement and contains work packages (deliverable's) at the
lowest level.
All of the following are project management tools dealing with scheduling
--Network Diagrams
--Gantt Charts
--Milestone Charts
Pricing is a function by which party?
Vendors / Contractors
What type of cost estimation determines that a project needs $x for concrete, $x
for asphalt, $x for specialized machinery, etc.?
Bottom-up
Quality planning is concerned with:
Meeting Project Standards
Cost of Quality, or the total cost of all efforts to achieve product quality include
all of the following:
Appraisal Cost
Failure Cost
Prevention Cost
Risk identification techniques include:
Brainstorming
The following is a benefit when all project personnel report directly to the project
manager rather than their functional managers?