Typical elements of the project charter include all of the following except - Answer A
Project objectives
B Project purpose
C The project manager's responsibility and authority
*D The resources required
Which process is the most dependent on the nature of the work being performed? It is
the process where the deliverables are created. - Answer A Create WBS
B Define Scope
*C Direct and Manage Project Execution
D Monitor and Control Project Work
Which is not part of the Control Scope process? - Answer A Making sure scope creep
does not occur on the project
B Managing project and product scope changes
C Making sure all requested preventive and corrective actions for project scope go
through the Perform Integrated Change Control process
*D Obtaining customer validation on the final deliverable
What are the five project management process groups? - Answer A Planning, concept,
communicating, administration, closeout
* B Monitoring and controlling, planning, executing, closing, initiating
C Inputs, outputs, controls, execution, planning
D Scope, schedule, cost, quality, risk response
You have three projects to choose from: Project A with Internal Rate of Return (IRR) of
20%, Project B with an IRR of 15%, and Project C with an IRR of 17%. Which one
would you choose? - Answer * A Project A
B Project B
C Project C
D None of the above
Project closure includes all of the following except - Answer A Archiving project records
B Conducting lessons learned
*C Verifying product scope
D Conducting a project audit
What documents the project deliverables, acceptance criteria, assumptions, and
constraints? - Answer A The contract statement of work
B Requirements documentation
C Project charter
* D Project scope statement
, Two projects are approximately equal in size. Project A takes four years to complete
and has Net Present Value of $200,000; and project B takes three years to complete
and has NPV of $300,000. Which project should you select? - Answer A Project A
*B Project B
C Project A if it can be reduced to three years
D Project B if it can reduced to NPV of $200,000
There are a number of creative group techniques that can be used to identify product
and project requirements. Which one takes a large number of ideas and groups them
for review and analysis? - Answer A Delphi technique
* B Affinity diagram
C Nominal group technique
D Mind mapping
There are a number of creative group techniques that can be used to identify product
and project requirements. Which one uses a voting process to prioritize ideas generated
in the brainstorming process? - Answer A Delphi technique
B Affinity diagram
*C Nominal group technique
D Mind mapping
The inputs to the Develop Project Plan process include - Answer A Outputs from
planning processes, historical information, organizational policies, constraints, and
assumptions
B Outputs from planning processes, expert judgment, organizational policies, and
Enterprise Environmental Factors
*C Outputs from planning processes, project charter, Organizational Process Assets
and Enterprise Environmental Factors
D Outputs from planning processes, expert judgment, organizational policies,
constraints, and assumptions
PMI® defines a project as having two distinctive characteristics. They are - Answer A
Program and project
* B Temporary and unique
C Product and project
D Cost and schedule
Select the statement that best completes the following statement: If the product scope
description is progressively elaborated, it - Answer * A Has less detail in early phases
and more detail in later phases of the project
B Has no documented detail in early phases of the project
C Requires more detail in early phases of the project
D Contains project requirements
When preparing the project charter, the author should include - Answer *A The business
need the project was undertaken to address