TOP PMG IMPORTANT QUIZ WITH
ANSWERS
,An activity that represents a major segment of work is a good example of a
milestone. Select one:
True
False
Project scope describes what you expect to deliver to your customers when
the project is complete.
Select one:
True
False
"To construct a high-quality, custom home within five months at costs not
to exceed $150,000" is best classified as
an exclusion
a milestone
an objective
a deliverable
a limit lOMoARcPSD|1670110
If a project is small and does not require an elaborate system to assign tasks,
which of the following is a good choice?
Work breakdown structure
Process breakdown structure
Responsibility
Organization breakdown structure
Priority matrix
All of the following are ways the WBS helps in managing projects EXCEPT
,it provides management with information appropriate to each level
can be used to define communication channels
as it is developed, organizational units and individuals can be assigned
responsibility of work packages
allows the project manager to establish the overall objective of the project.
with cost and time estimates the WBS makes it possible to plan, schedule and
budget the project lOMoARcPSD|1670110
Significant events in a project that occur at a specific point in time, are
natural control points, and are easily recognized by project participants are
known as ___________.
activities
milestones
due dates
tasks
kill points
One of the primary jobs of a project manager is to manage the trade-offs among
time, cost, and performance. To do so, the project manager must define and
understand the ___________ of the project.
project charter
communications plan
priorities
, WBS
lOMoARcPSD|1670110
requirements
Which of the following items has to do with the expected measurable outputs
over the life of the project?
Milestones
Project objective
Justification
Deliverables
Product scope description
The lowest element in the hierarchical breakdown of the WBS is
a lowest sub-deliverable
a deliverable
a work package
an object
a cost account
ANSWERS
,An activity that represents a major segment of work is a good example of a
milestone. Select one:
True
False
Project scope describes what you expect to deliver to your customers when
the project is complete.
Select one:
True
False
"To construct a high-quality, custom home within five months at costs not
to exceed $150,000" is best classified as
an exclusion
a milestone
an objective
a deliverable
a limit lOMoARcPSD|1670110
If a project is small and does not require an elaborate system to assign tasks,
which of the following is a good choice?
Work breakdown structure
Process breakdown structure
Responsibility
Organization breakdown structure
Priority matrix
All of the following are ways the WBS helps in managing projects EXCEPT
,it provides management with information appropriate to each level
can be used to define communication channels
as it is developed, organizational units and individuals can be assigned
responsibility of work packages
allows the project manager to establish the overall objective of the project.
with cost and time estimates the WBS makes it possible to plan, schedule and
budget the project lOMoARcPSD|1670110
Significant events in a project that occur at a specific point in time, are
natural control points, and are easily recognized by project participants are
known as ___________.
activities
milestones
due dates
tasks
kill points
One of the primary jobs of a project manager is to manage the trade-offs among
time, cost, and performance. To do so, the project manager must define and
understand the ___________ of the project.
project charter
communications plan
priorities
, WBS
lOMoARcPSD|1670110
requirements
Which of the following items has to do with the expected measurable outputs
over the life of the project?
Milestones
Project objective
Justification
Deliverables
Product scope description
The lowest element in the hierarchical breakdown of the WBS is
a lowest sub-deliverable
a deliverable
a work package
an object
a cost account