2024
A(n) ____________ is a model of a real project-what you want to happen or what you
think will happen. - Answ Project Schedule
(Ch 1)
A(n) ____________ is a logical connection between tasks that controls sequence and
dependency. - Answ Link
(Ch 1)
A group of closely related tasks that encompass a major section of your project is a(n)
____________. - Answ Phase
(Ch 1)
A(n) ____________ is a scheduling tool that determines the standard working time and
nonworking time for the project, resources, and tasks. - Answ Calendar
(Ch 1)
A(n) ____________ is a pre-defined file that can be used as a starting point to create a
project schedule. - Answ Template
(Ch 1)
A(n) ____________ is supplemental text that you can attach to a task, resource, or
assignment. - Answ Note
(Ch 1)
A(n) ____________ is added to the project calendar to denote something different from
the standard working times. - Answ Exception
(Ch 1)
A task whose start or end date determines the start or finish of another task or tasks is
a(n) ____________. - Answ Predecessor
(Ch 1)
, A(n) ____________ represents a significant event reached within the project or
imposed upon the project. - Answ Milestone
(Ch 1)
A(n) ____________ represents the actual individual work activities that must be done to
accomplish the final goal. - Answ Tasks
(Ch 1)
defines the working and nonworking time for an individual resource - Answ Resource
Calendar
the maximum capacity of a resource to accomplish tasks - Answ Max. Units
consumable items used up as the tasks in a project are accomplished - Answ Material
Resource
the base calendar that provides default working times for an entire project - Answ
Project Calendar
a resource that doesn't depend on the amount of work on a task or the duration of a
task - Answ Cost Resource
a resource that doesn't depend on the amount of work on a task or the duration of a
task - Answ Work Resource
specifies default working and nonworking times for a resource, a project, or a task -
Answ Base Calendar
when and how much of a resource's time can be assigned to work on tasks - Answ
Availability
the people, equipment, money, and materials used to complete the tasks in a project -
Answ Resources
a way of documenting information about resources, tasks, and assignments - Answ
Note
A(n) ________ is the matching of a specific resource to a particular task to do work. -
Answ Assignment
Assigning a(n) ______ or ________ resource to a task will not affect the duration of the
task. - Answ Cost or Material