Cost Rate Table - : resource pay rates that are stored on the Costs tab of the Resource
Information dialog box
Under allocated - : the work assigned to a resource is less than the resource's
maximum capacity
Variable Consumption Rate - : the amount of the material resource consumed is
dependent upon the duration of the task
units - : the measurement of a resource's capacity to work
allocation - : the portion of a resource's capacity devoted to work on a specific task
fixed consumption rate - : an absolute quantity of material resources will be used, no
matter the duration of the task
over allocated - : a resource is assigned to do more work than can be done within the
normal capacity of the resource.
resource leveling - : the process of delaying or splitting a resource's work on a task to
resolve an over allocation
fully allocated - : the total work of a resource's task assignments is exactly equal to that
resource's work capacity
max. units - : the maximum capacity of a resource to accomplish work
Resource leveling cannot always resolve all resource over allocations. - : True
A resource cannot have both a cost per use and a cost derived from its pay rate. - :
False
Resource leveling never changes who is assigned to tasks, or the total work value of
those assignments. - : True
You can manually resolve a resource over allocation by replacing the over allocated
resource with another resource. - : True
You can assign two types of material consumption rates in Microsoft Project. - : True
The settings in the Resource Leveling dialog box apply to all of the project schedules
you work with in Microsoft Project. - : True
, You can have up to six cost rate tables for a resource. - : False
It is not acceptable to allow a minor over allocation to remain in a schedule. - : False
The default rate table in Microsoft Project is Rate Table 1. - : False
When a variable consumption rate is assigned to a material resource, and the duration
of the task to which it is assigned changes, so do the calculated amount and cost of the
material resource. - : True
_______ is a quick way to view only the task or resource information you choose. - :
Autofilter
In the Sort dialog box, you can utilize up to _______ nested levels of sort criteria. - :
Three
When you use grouping, the ________ data rows are set off by a colored background. -
: Summary
When AutoFilter is turned on, small ________ are visible next to the column headings.
- : Arrows
A way to reorder task or resource information in a table and to display summary values
according to various criteria you can choose is called a(n) __________. - : Group
The _______ dialog box shows you all of the predefined filters that are available to you
for tasks or resources. - : More Filters
A(n) __________ is a way of ordering task or resource information in a view by the
criteria you specify. - : Sort
When you apply a filter, you may see gaps in the order of the ________ - : Task IDs
When you sort data in your project, the sort applies to the active ________, no matter
which table is displayed. - : view
A tool that enables you to see or highlight in a table only the task or resource
information that meets criteria you choose is a(n) __________. - : Filter
1. The simplest way to reorganize data in Microsoft Project is by
a. filtering.
b. sorting.
c. grouping.
d. AutoFiltering - : b. sorting