For a duration of one elapsed minute, the entry in the Duration column would appear as
__________.term-6
A. 1em
B. 1eminute
C. 1emn
D. 1emin - Answ D
"Tester, Maintenance Supervisor, digital camera, Jeff Pike" are all examples of which of
the following?
A. work resource
B. job titles
C. cost resource
D. material resource - Answ A. work resource
The start date of the predecessor task determines the start date its successor task.
Which type of task relationship should be used?
A. finish-to-start
B. finish-to-finish
C. start-to-start
D. start-to-finish - Answ C. start-to-start
By establishing resources in your project file, you can track __________.
A. who is available to work
B. the type of work each resource can do
C. when each resource is available to work
D. all of the above - Answ D. all of the above
In order to use Project properly, you must always enter cost information into a project
plan.
A. True
B. False - Answ B. False
Which of the following resource(s) has no effect on the total amount of work scheduled
to be performed on a task.
A. material
B. work
C. group
D. equipment - Answ A. material
, Which of the following is the default opening view when you start Project?
A. Gantt Chart
B. Calendar
C. Network Diagram
D. Task Sheet - Answ A. Gantt Chart
_________ __________ should be used when a task must be scheduled over the
weekend, such as concrete curing. - Answ Elapsed duration
You have a material resource called "drywall" with a material label of "4ft. x 8ft. sheet.
Which of the following would be an appropriate entry in the Standard Rate field?"
A. $10/hr
B. $10
C. $10/minute
D. both a and b - Answ B. $10
The scheduling of individual tasks is dictated by which of the following calendars?
A. base
B. task
C. project
D. resource - Answ B. task
When first establishing resources, the resource calendar for each resource is identical
to which other calendar? - Answ project calendar
A project phase is best represented by a __________.
A. subproject
B. minor phase
C. summary task
D. subtask - Answ C. summary task
A piece of equipment cannot have a calendar applied to it.
A. True
B. False - Answ B. False
A resource calendar can be applied to which of the following?
A. people resources
B. material resources
C. equipment resources
D. both a and c - Answ D. both a and c
The total length of working and nonworking time you expect a task will take would best
be described as the ____________ ______________. - Answ elasped duration
A(n) __________ represents a significant event reached within a project or imposed
upon a project. - Answ Milestone