Advanced Project Management
Lecture 1

Uncertainties attached to WPs (Van Bueren et al., 2003)
– Cognitive uncertainty (as in Rittel & Weber, 1973): Unknown/unclear how causes and
consequences of a problem exactly are related (lack of [scientific] knowledge);
– Strategic uncertainty: Due to many actors involved, different views on nature of problem and
strategies to deal with them
– Institutional uncertainty: Decision-making take place in different institutional arenas (ranging
from local to international and different levels of ‘maturity’)

Type of problems (Roberts, 2000)
• Type 1 problems: “Simple problems”. High consensus on problem definition and
solution among stakeholders. Standard routines and procedures to deal with
problem.
• Type 2 problems: “Complex problems”. Agreement on problem, but not on solution.
Conflict among stakeholders and decision-making process more complex. (Example:
Plastic waste pollution in oceans)
• Type 3 problems: No agreement on problem or solution. Typically a wicked problem.
(Example: Immigration policies)

Type 3 Coping Strategies
1.Authorative strategies:
– Type 3 problem + power not dispersed.
– Put problem in hands of a few stakeholders
– Few stakeholders selected on basis of e.g., knowledge, expertise, status, position, coercive
power
– Other stakeholders accept ‘lower’ power position
– Advantages:
• Reducing #stakeholders = reducing complexity
• Problem solving goes quicker
• Using experts, more professional
– Disadvantages:
• Authorities/experts can be wrong
• Lost opportunity for community-wide learning

2.Competitive strategies:
– Stakeholders assume ‘zero-sum-game’.
– Central is search for power (ability to get what one wants against resistance)
– Power is contested
– Advantages:
• Competition often breeds creativity
• Challenging institutionalization of power (some you win/lose)
– Disadvantages:
• Produce extreme behaviors
• Increase costs (e.g. disputes)

, 3.Collaborative or network strategies:
– Joining forces with (number of) stakeholders = trying to create synergy or win-win game
– Enlarging the pie
– Alliances, partnerships, joint ventures, networks
• Advantages, e.g.
– Sharing costs and benefits
– Sharing risks
– Better output
– Eliminating redundancies and increasing efficiency
• Disadvantages, e.g.
– Higher transaction costs
– Higher probability of conflicts

Tertius gaudens orientation (Georg Simmel): is a third party who profits or benefits from
competition amongst two others. The third party can gain tremendous power. Sparse
networks and structural holes are ideal strategic position for the creation of new ideas and
for information flows.

Tertius Iungens orientation (David Obstfelt): "the third who joins“. These same networks are
poorly suited to action and resource mobilization. Thus: dense social networks to marshal
resources

From dyad to triad (= multi-actor)
• From restricted (social) exchange (dyadic level)
– i.e., two parties directly exchange (favors)
• To generalized (social) exchange (> dyadic level)
– i.e. takes place among a group of a least 3 parties and there is no direct reciprocity
(delayed)
• Consequence (esp. at inter-organizational level)
– Less reliance on formal structures (hierarchy & rules) only
– More reliance on social (informal) mechanisms (trust, socialization, reputation), but
very hard to observe

Temporary goal-directed whole networks or temporary organizations are:
– Temporary inter-organizational systems of legally autonomous but functionally
interdependent organizations that interact to coordinate their efforts for the
accomplishment of a joint outcome in a limited amount of time (which is ex ante defined)

Lecture 1: Stakeholder Management
Stakeholder: Any person, group or organisation who can be positively or negatively impacted by, or
cause an impact on, the action or activities in the project.

Stakeholder Management is:
• Project stakeholder management are all the purposeful activities towards stakeholders to enhance
project success.
• It consists of the identification, assessment, prioritisation, engagement and monitoring of
stakeholders.

Written for

Institution
Study
Course

Document information

Uploaded on
April 2, 2024
Number of pages
14
Written in
2023/2024
Type
SUMMARY

Subjects

$5.53
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller
Seller avatar
koen-smits

Get to know the seller

Seller avatar
koen-smits Tilburg University
Follow You need to be logged in order to follow users or courses
Sold
11
Member since
2 year
Number of followers
10
Documents
7
Last sold
1 year ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions