QUESTIONS AND CORRECT ANSWERS
[ACTUAL EXAM 100%] GRADED A+
Cadence and Synchronization help reduce uncertainty and
manage what?
-Product management
-Capacity allocation
-Other commitments
-The variability in solution development - ANS✔✔---The
variability in solution development
How does SAFe handle the "fear of conflict" team
dysfunction?
-Review results to drive accountability
-Empirically review results at the end of every iteration and
release
-Have teams engage in Retrospectives
,-Use Scrum to create safe environment for conflict -
ANS✔✔---Use Scrum to create safe environment for
conflict
What does SAFe's CALMR approach apply to?
-Servant Leadership
-Economic Framework
-Continuous Deployment
-DevOps - ANS✔✔---DevOps
An effective SAFe Scrum Master helps the team improve
in areas including quality, predictability, flow, and where
else?
-Continuous delivery
-Team metrics
-Relentless improvement
-Risk mitigation - ANS✔✔---Team metrics
What foundational issue most often leads to team
dysfunction?
-Weak Lean-Agile leadership
-Avoidance of accountability
-Lack of commitment
-Absence of trust - ANS✔✔---Absence of trust
What is an IP Iteration anti-pattern?
, -Identify opportunities for innovation spikes or hackathons
-Identify infrastructure improvements
-Plan work for the IP Iteration during PI Planning
-Allow for cadence-based planning - ANS✔✔---Plan
work for the IP Iteration during PI Planning
An effective SAFe Scrum Master elevates people
problems with strict confidence to the appropriate levels
when necessary, but only after what has happened?
-They have repeatedly directed the team member to take
appropriate action
-A team member consistently disagrees with the Scrum
Master
-The team consistently fails to meet consecutive PI goals
-Coaching and internal processes have failed to achieve
the objective - ANS✔✔---Coaching and internal
processes have failed to achieve the objective
What are two common anti-patterns during PI Planning?
(Choose two.)
-The Team Backlog is applied to a very targeted part of
the organization
-A detailed plan becomes the goal, rather than alignment
-The team determines where changes should be targeted