A project has three sequences of activities (paths), two of which are critical. The critical paths of this
project can be characterized in the following way:
A. The slack times for each task in the entire project are zero.
B. The chain of activities (from start to finish) that has the largest sum of activity durations.
C. The early start date and early finish date are always the same for each activity on the critical path.
D. To reduce the project duration, you must reduce the slack time of a task on the critical path.
E. None of the above are correct.
B. The chain of activities (from start to finish) that has the largest sum of activity durations.
Consider the following regarding learning curves:
I. The mathematical relationship between time to perform a task and experience is generally linear.
II. A learning rate of 85% is superior to a learning rate of 80%III. The value of n is always negative for
learning to occur.
IV. The value for k can be read directly from the Excel regression output (i.e. no transformation is
needed). Choose the correct response below:
A. items I and IV are false; items II and III are true
B. items I, II and IV are false; item III is true
C. items III and IV are false; items I and II are true
D. items II, III and IV are false; item I is true
E. all of the statements are true
B. items I, II and IV are false; item III is true
Current issues in OSCM do not include:
A. Coordinating relationships between organizations
B. Making senior management aware that OSCM can be a competitive weapon
C. The triple bottom line
D. Managing customer touch points
E. Increasing global supply chain employment
E. Increasing global supply chain employment
Management decisions within the operations function can be classified into the following levels:
A. Strategic and tactical.
B. Tactical, strategic, and transformation.
C. Strategic, transformation, and operational planning and control.
D. Strategic, tactical, and operational planning and control.
E. Transformation, strategic, and tactical.
D. Strategic, tactical, and operational planning and control.
What is the "Big Question" answered by the Operations function (simplified):
A. Who?
B. How?
, C. What?
D. When?
E. none of the above
B. How?
The service sector is now the largest employer of US citizens. As we look ahead to the future, and
knowing services are the "younger sector, yet fastest growing sector", which of the following
statements is most accurate?
A. Productivity gains in the service sector will be easier to generate than productivity gains in the
manufacturing sector.
B. Productivity gains in the service sector will be a bigger challenge than productivity gains in the
manufacturing sector.
C. Productivity gains in the service sector will be impossible to attain.
D. Productivity gains in both sectors will be equally attainable.
E. None of the above statements are true.
B. Productivity gains in the service sector will be a bigger challenge than productivity gains in the
manufacturing sector.
The Strategic Planning Process is characterized by which of the following activities?
A. Segment the market according to product group.
B. Consider expansion of capital assets.
C. Measure growth in productivity each month.
D. Both A and B are correct.
E. A, B and C are all correct.
D. Both A and B are correct.
Which of the following is a definition of productivity? (think of the formula here)
A. The degree of goal attainment
B. A ratio of input per unit of output
C. The effectiveness of capital and equipment
D. Labor hours required to produce a specific product
E. The amount of output per hour worked
E. The amount of output per hour worked
Which of the following measures is a partial productivity measure?
I. Output/Labor
II. Output/Materials
III. Output/(Labor+Energy+Capital)
IV. Output/Inputs
I and II only
II and III only
III and IV only
III only
IV only
I and II only