1) In remedy situations, the Contracting Officer’s Representative’s oversight duties and
documented files are key to determining the course of action for the government to take.
The COR contributes by: [Identify how a COR deals with non compliance or poor
performance.]
All of the answers are correct
Monitoring
Documenting
Communicating
2) When the contractor is delinquent on contract performance, the two types of
delinquency notices sent by the Contracting Officer are: [Discuss when and why
schedule compliance must be brought to the attention of the KO] [Remediation Accessed
:N]
A Cure Notice and a Show Cause Notice. The two notices may be used sequentially or,
depending on the time left in performance, only a single notice might be used.
A Second Chance Notice and a Show Cause Notice. The two notices may be used
sequentially or, depending on the time left in performance, only a single notice might be
used.
A Cure Notice and a Termination Notice. The two notices may be used sequentially or,
depending on the time left in performance, only a single notice might be used.
A Termination for Default Notice and a Cure Notice. The two notices may be used
sequentially or, depending on the time left in performance, only a single notice might be
, used.