Correct Answers Graded A+
In project schedule management, which process primarily involves checking and managing changes to
the project schedule?
A. estimating activity durations
B. developing the schedule
C. controlling the schedule
D. estimating activity resources
D. estimating activity durations
In project schedule management, which process primarily involves checking and managing changes to
the project schedule?
A. estimating activity durations
B. developing the schedule
C. controlling the schedule
D. estimating activity resources
C. controlling the schedule
Which document is most likely to include planned project start and end dates which serve as the
starting points for a detailed schedule?
A. resource breakdown structure
B. milestones list
C. organizational process assets update
D. project charter
D. project charter
Which term is used for a significant event on a project that normally has no duration?
A. milestone
B. activity attribute
C. activity sequence
D. schedule baseline
A. milestone
In project schedule management, the main goal of which process is to ensure that the project team
has a complete understanding of all the work they must do as part of the project scope so they can
start scheduling the work?
A. defining activities
B. estimating activity durations
C. estimating activity resources
D. controlling the schedule
A. defining activities
In project schedule management, what is the next step after defining project activities?
A. planning schedule management
B. determining their dependencies