Establishing the project scope and identifying risks are activities of ________ agile phase
Inception
In which agile phase the Beta testing is performed?
Transition
Which of the following is NOT an agile framework?
Linear Programming
_______ framework focuses on identifying and eliminating wastage in the software development
process.
Lean
In ________ programming, one programmer writes the code & other programmer proofreads &
determines what to do next.
Pair
In Kanban Board, Work in Progress (WIP) Limits are the maximum number of cards that can be in one
column.
True
Who are ultimately responsible for the quality management of the projects?
Project Managers
Which Project quality management process periodically evaluates overall project performance to
ensure the project will satisfy the relevant quality standards?
Performing quality assurance
_______ addresses how well a product or service performs the customer's intended use?
Performance
While performing quality assurance, what generates ideas for quality improvements by comparing
specific project practices to those of other projects?
Benchmarking
________ is the ability of a product or service to perform as expected under normal conditions.
Reliability
__________ trace complaints about quality problems back to the responsible production operations.
Cause and effect diagrams
Which of the following is based on the 80-20 rule?