Which process involves working with stakeholders to create the document that formally authorizes a
project?
A. Developing the project charter
B. Developing the preliminary project scope statement
C. Developing the project management plan
D. Performing integrated change control
A. Developing the project charter
Which process includes defining project scope, benefits, and constraints?
A. project planning
B. business area analysis
C. resource allocation
D. information technology strategy planning
A. project planning
What is the first step in the planning process?
A. tie the information technology strategic plan to the organization's overall strategic plan
B. perform a business area analysis
C. start defining potential IT projects in terms of their scope, benefits, and constraints
D. choose which projects to do and assigning resources to work on them
A. tie the information technology strategic plan to the organization's overall strategic plan
What term is used for benefits minus costs?
A. cost of capital
B. cash flow
C. discount factor
D. opportunity cost of capital
B. cash flow
Which information is included in a business case?
A. business need for the project
B. relevant government or industry standards
C. project objective, high-level requirements, and time and cost goals
D. policies, procedures, guidelines, and systems that influence a project's success
C. project objective, high-level requirements, and time and cost goals
What document used to coordinate all project planning documents and help guide a project's
execution and control?
A. project management plan
B. statement of work
C. scope statement
D. business case
A. project management plan