Which term describes a product produced as part of a project?
A. variance
B. scope
C. deliverable
D. work package
C. deliverable
Which statement best describes scope?
A. each level of work that is outlined in a work breakdown structure
B. end product created as part of a project that is delivered to the client
C. tasks that are decomposed into smaller tasks in a work breakdown structure
D. work involved in creating the products and the processes used to create them
D. work involved in creating the products and the processes used to create them
Which action involves reviewing the project charter, requirements documents, and organizational
process assets to create a scope statement, adding more information as requirements are developed
and change requests are approved?
A. Creating scope
B. Defining scope
C. Controlling scope
D. Validating scope
B. Defining scope
Creating the WBS is a subprocess associated with which process in project scope management?
A. planning
B. monitoring and controlling
C. closing
D. executing
A. planning
We have an expert-written solution to this problem!
Which document contains a deliverable-oriented grouping of the work involved in a project that
defines the total scope of the project?
A. project charter
B. business case
C. project scope statement
D. work breakdown structure
D. work breakdown structure
Which task is at the lowest level of the WBS?
A. variance
B. objective
C. deliverable