Construction Exam With Correct
Questions And Answers 2024
The Clean Water Act - CORRECT ANSWERS-The 1970's law that set into place the
regulation of storm water
NPDES - CORRECT ANSWERS-Requirements for managing storm water activity on a
construction site are outlined in the following regulation
Discharge From Contaminated Ground Water - CORRECT ANSWERS-Never an
allowable discharge from a construction site
A notice of termination can be filed when? - CORRECT ANSWERS-All construction
activity, inside and outside of the building is complete. Permanent stabilization has been
verified.
The storm water notice of intent must be submitted? - CORRECT ANSWERS-After the
SWPPP is prepared and before starting construction.
Potential pollutant sources stored on a construction site may include? - CORRECT
ANSWERS-Petroleum storage tanks, fertilizer, lime, and masonry materials.
The SWPPP implementation sequence may be modified? - CORRECT ANSWERS-
After consulting with the project SWPPP designer (CEC) and if required, the project
owner and receiving written approval.
A SWPPP site map will show all of the following? - CORRECT ANSWERS-Location of
BMP's, Phasing & Sequence, Limits of Disturbance
Which of the following information is to be posted at the entrance to the site? -
CORRECT ANSWERS-Construction site notice, permit authorization, location of
SWPPP
Which of the following is not a beneficial use water? - CORRECT ANSWERS-Flushing
water down a storm drain
When installing and maintaining a check dam make sure...? - CORRECT ANSWERS-
The low point (overflow) of the check dam is in the middle of the channel