With 100%Correct Answers Latest Update 2024
The 1970s law that set into place the regulation of stormwater is - Correct Answer-The
clean water act
Requirements for managing stormwater activity on a construction site are outlined in the
following regulation - Correct Answer-NPDES
Which of the following is never an allowable stormwater discharge from a construction
site - Correct Answer-Discharge from contaminated ground water
The notice of termination can be filed when - Correct Answer-All construction activity,
inside and outside of the building, is complete and permanent stabilization has been
verified as adequate to meet permit requirements
Relative to stormwater permitting all of the following must occur before construction
starts except - Correct Answer-Submit the notice of termination (NOT)
The stormwater notice of intent (NOI) must be submitted - Correct Answer-After the
SWPPP is prepared and before starting construction
Potential pollutant sources stored on a construction site may include - Correct Answer-
1. Petroleum storage tanks
2. Soil sediments
3. Masonary material
4. ALL OF THE ABOVE
The SWPPP inflammation sequence may be modified - Correct Answer-After consulting
with the project SWPPP Designer (CEC) and, if required, the project owner and
receiving written approval
A SWPPP site map will show all of the following except - Correct Answer-Notices of
violation
Which of the following information is to be posted at the entrance of the site - Correct
Answer-1. Construction site notice
2. Permit authorization
3. Location of SWPP
4. ALL OF THE ABOVE
Which of the following is NOT A beneficial use of water - Correct Answer-Flushing a
spill down a storm drain
, When installing and maintaining a check dam make sure - Correct Answer-The low
point (overflow) of the check dam is in the middle of the channel
To reduce the possibility of undercutting in channels, you should - Correct Answer-
Install filter fabric under rock and similar materials placed within the stormwater
conveyance
The good housekeeping section of the SWPP must include all BUT which of the
following - Correct Answer-Post construction stormwater management procedures
Runoff controls include all but which of the following - Correct Answer-Rolled erosion
control products
Which erosion control best management practice increases water filtration, dissipates
rainfall energy and slows over flow of stormwater - Correct Answer-Vegetation
Of the following factors that influence erosion rates, the one a contractor has the most
control over (only select one) is - Correct Answer-Groundcover
Temporary stabilization should be implemented - Correct Answer-Immediately on all
disturbed areas that are likely to or will remain inactive for 14-days or more
The primary purpose of a construction exit is - Correct Answer-To remove sediment
from construction site vehicles and minimize trackout
Common types of erosion include all of the following except - Correct Answer-
Sedimentation
Proper spill management should include all of the following EXCEPT - Correct Answer-
Installation of a spill pit on your construction site
The best location for portable toilets on your construction site is - Correct Answer-On
ground level, in low construction traffic areas
The following must be marked on site maps in the job site trailer as work progresses -
Correct Answer-The dates when BMP changes or additions take place
While inspecting field BMP's the SWPPP inspector should perform all of the following
EXCEPT - Correct Answer-Assume BMP's are in good condition from a distance
If your site is inspected by US EPA, or another regulatory agency, you should: - Correct
Answer-1. Be courteous
2. Attend their inspection
3. Allow access to sight and documentation
4. ALL OF THE ABOVE