TEST RM#1 WITH 100% CORRECT
ANSWERS { GRADED A+}
According to FERC, environmental Inspectors shall have
_____________ status in regards to all other craft inspectors. -
✔✔Equal
According to Title 49 CFR 195, any new pipe with a diameter greater
than ___________ inches must be marked with the specification, the
SMYS/Grade, and pipe size. - ✔✔4.5
This legislation covers hazardous substance, site contamination, and
cleanup - ✔✔Comprehensive environmental recovery, compensation,
and liability act.
,A blueprint showing the exact route of a pipeline and virtually all of the
knowledge that exist for that pipeline when constructed is called a
______________? - ✔✔Alignment sheets
In area is considered oxygen deficient if the oxygen level is below
___________ % - ✔✔19.5
During a pressure test, if a leak develops on a connection, yomust
depressurize to a safe level and then - ✔✔re-tighten the connections
Which listed non-destructive testing method is specified in API 1104? -
✔✔RT examination
Prior to a hydrotest, ensure that the _______ has approved the de-
watering location. - ✔✔Environmental Inspector
As an inspector, you should ensure that there is always a (n) on a site
with an open excavation. - ✔✔designated competent person
, Calculate the top width of a bell hole excavation using the following
information: Depth of ditch: 8 feet Bottom Width: feet Soil type: C -
✔✔30 : formula soil type C : 3 x depth + bottom width = top width
Demonstrated ability to apply knowledge and skills. - ✔✔competence
According to the EPA, which phase covers containment,
countermeasures, cleanup, and disposal for response for oil removal
after a spill. - ✔✔Phase III
Which refarence in 40 CFR Part 300 claifies procedures for planning
and implementing off-site response actions for hazardous substances? -
✔✔300.440
The color code for marking oil & gas buried utilities during sweep is
_____________? - ✔✔yellow
According to OSHA, excavations that are less than 5' in depth & the
examination of the ground by a competent person provides no indication
of a potential cave-in, is not required to have any type of protection
system. - ✔✔True