DBIA EXAM I
In which project delivery method is the construction team brought on
AFTER design, with open bidding? - ANSWER---- DBB
In the planning phase, Influence has a _____ impact on the project. -
ANSWER---high
In which project delivery method is the construction team brought on
EARLY, facilitating fast-tracking? - ANSWER---DB
Spearin Doctrine: Owner hiring designers provides contractors two
specific implied warranties: Plans and specs are _____; Plans and specs
are suitable for _____ _____. - ANSWER---- accurate
- intended purpose
What are the 5 types of project delivery systems? - ANSWER---- DB
- DBB
- CMAR
- IPD
- Multiple prime contracting
, DBIA EXAM 1, EXAM 2 AND EXAM 3 NEWEST 2024
ACTUAL EXAM COMPLETE 500 QUESTIONS AND
CORRECT DETAILED ANSWERS (VERIFIED ANSWERS)
|ALREADY GRADED A+
_____ is a linear sequential process. - ANSWER---DBB
In DBB, the A/E is typically selected on _____ and the GC is typically
selected on _____ _____. - ANSWER---- qualifications
- low price
In DBB, design is fully completed _____ input from the GC. -
ANSWER---without
In _____, the A/E is acting in the owner's interests. - ANSWER---DBB
Who controls the design team selection in DBB? - ANSWER---The
Owner
The _____ project delivery method is well established and understood. -
ANSWER---DBB
Which project delivery system is consistent with public sector
procurement laws and the most prevalent delivery system through the
20th century? - ANSWER---DBB
, DBIA EXAM 1, EXAM 2 AND EXAM 3 NEWEST 2024
ACTUAL EXAM COMPLETE 500 QUESTIONS AND
CORRECT DETAILED ANSWERS (VERIFIED ANSWERS)
|ALREADY GRADED A+
In DBB the _____ _____ is incompatible with expediting project
delivery. - ANSWER---Linear sequence
in _____, the contractor's input is absent during the design process. -
ANSWER---DBB
In DBB, the Owner has a "_____ of _____ relationship" with the A/E. -
ANSWER---Standard of Care Relationship
In DBB, the Owner has a "_____ relationship" with the Contractor. -
ANSWER---Spearing Relationship
What 2 methods of selection (procurement methods) does CMAR use? -
ANSWER---- QBS
- Best Value
Who provides the pre-construction services for CMAR? - ANSWER---
Contractor
What kind of contracting approach is usually used in CMAR? -
ANSWER---Negotiated GMP
, DBIA EXAM 1, EXAM 2 AND EXAM 3 NEWEST 2024
ACTUAL EXAM COMPLETE 500 QUESTIONS AND
CORRECT DETAILED ANSWERS (VERIFIED ANSWERS)
|ALREADY GRADED A+
What is special about the estimating process in CMAR? - ANSWER---it
is an open-book
Which delivery methods have the chance to fast track the schedule? -
ANSWER---- DB
- CMAR
In CMAR, the construction cost is determined _____ the design is
completed. - ANSWER---before
In CMAR, the Owner procures and manages designers and contractors
under (one / two separate) contracts? - ANSWER---two separate
In CMAR, the _____ negotiates the full commercial deal. - ANSWER---
Owner
In CMAR, what is the direct contractual relationship between the
contractor and designer? - ANSWER---There is no direct contractual
relationship
In CMAR, there is _____ public sector authority for its use. -
ANSWER---limited