API 653 Exam Prep Closed Book 2024 Questions & Answers | 100% Correct | Verified API 653 defines a "Storage tank engineer" as: A) A registered professional engineer in structural steel fabrication B) Person or organization who is knowledgeable and experienced in the engineering disciplines associated with evaluating the integrity and reliability of aboveground storage tanks C) the engineering department of a contractor who makes repairs to aboveground storage tanks D) A professional engineer who is also an authorized API 653 inspector - B Similar service is means of estimating corrosion rates that: A) Is Seldom used as a means of scheduling internal inspection intervals B) Ignores environmental factors in the determination of corrosion rates C) May be used in addition to or in lieu of actual measurement of corrosion rates D) Is generally considered as the best methodology for establishing the inspection intervals - C Controlled Deposition welding methods, in lieu of PWHT, is limited to: A) P-1 materials B) P-1 and P-3 Materials only C) P-1, P3, and P4 materials only D) P-5A materials - C Inspection hold points, for tank reconstruction, shall be designated by: A) The authorized inspector B) An engineer experienced in storage tank design C) Agreement between tank owner/user and reconstruction contractor D) Agreement between and engineer and the authorized - AAll repair and alteration work shall be approved at all designated hold points and after completion: A) Need not be approved if approved will delay work progress B) By the repair organization of the repairs were done according to the specified repair and/or alteration procedures C) By the authorized inspector or experienced storage tank engineer D) By the authorized inspector only - C Alterations to storage tanks, which comply with API 650, must be authorized by: A) The owner/user B) The storage tank engineer C) The authorized inspector D) The repair organization - B A record of non-essential variables used during welding of the test coupon is: A) Optional on the PQR B) Optional on the WPS C) Required on the PQR D) Required on the WPQ - A Cracks is the shell to bottom weld: A) Shall be evaluated per the "As built" Standard B) Shall be removed C) Shall be evaluated on a case by case basis D) Shall be evaluated per API 579 - B What welding process is most widely used in the repair of process equipment? A) GMAW B) GTAWC) SMAW D) FCAW - C The owner has decided to install a new bottom in an AST. The new bottom will be installed through existing tombstone reinforcing plates. One Method is to remove the lower portion of the reinforcing plate. After the new or replaced section is installed, the splice weld shall: A) Visually examined only B) Magnetic particle examined only C) Liquid penetrate examined only D) Ultrasonic shear wave examined only - B Which of the following is an advantage of thick film reinforced tank bottom lining? A) easier to apply than thin film B) initial cost is typically less than thin film C) Provides greater resistance to moisture ingress permeation D) Generally more accurate MFL floor scans - C The purpose of reviewing the welder performance qualification (WPQ) is to: A) Verify that welder are qualified to perform the welding given its position and process B) Verify that welds made in compliance with the WPS meet requirements C) Verify that the welding procedure specification can produce quality welds D) Verify that welders are qualified to perform the welding, including all essential and nonessential variables - A The recommended type of internal floating roof is the: A) Double Deck B) Annular pontoon C) Pan type D) Sing

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

API 653 Exam Prep Closed Book 2024
Questions & Answers | 100% Correct |
Verified
API 653 defines a "Storage tank engineer" as:

A) A registered professional engineer in structural steel fabrication

B) Person or organization who is knowledgeable and experienced in the engineering disciplines
associated with evaluating the integrity and reliability of aboveground storage tanks

C) the engineering department of a contractor who makes repairs to aboveground storage tanks

D) A professional engineer who is also an authorized API 653 inspector - ✔✔B



Similar service is means of estimating corrosion rates that:

A) Is Seldom used as a means of scheduling internal inspection intervals

B) Ignores environmental factors in the determination of corrosion rates

C) May be used in addition to or in lieu of actual measurement of corrosion rates

D) Is generally considered as the best methodology for establishing the inspection intervals - ✔✔C



Controlled Deposition welding methods, in lieu of PWHT, is limited to:

A) P-1 materials

B) P-1 and P-3 Materials only

C) P-1, P3, and P4 materials only

D) P-5A materials - ✔✔C



Inspection hold points, for tank reconstruction, shall be designated by:

A) The authorized inspector

B) An engineer experienced in storage tank design

C) Agreement between tank owner/user and reconstruction contractor

D) Agreement between and engineer and the authorized - ✔✔A

,All repair and alteration work shall be approved at all designated hold points and after completion:

A) Need not be approved if approved will delay work progress

B) By the repair organization of the repairs were done according to the specified repair and/or alteration
procedures

C) By the authorized inspector or experienced storage tank engineer

D) By the authorized inspector only - ✔✔C



Alterations to storage tanks, which comply with API 650, must be authorized by:

A) The owner/user

B) The storage tank engineer

C) The authorized inspector

D) The repair organization - ✔✔B



A record of non-essential variables used during welding of the test coupon is:

A) Optional on the PQR

B) Optional on the WPS

C) Required on the PQR

D) Required on the WPQ - ✔✔A



Cracks is the shell to bottom weld:

A) Shall be evaluated per the "As built" Standard

B) Shall be removed

C) Shall be evaluated on a case by case basis

D) Shall be evaluated per API 579 - ✔✔B



What welding process is most widely used in the repair of process equipment?

A) GMAW

B) GTAW

,C) SMAW

D) FCAW - ✔✔C



The owner has decided to install a new bottom in an AST. The new bottom will be installed through
existing tombstone reinforcing plates. One Method is to remove the lower portion of the reinforcing
plate. After the new or replaced section is installed, the splice weld shall:

A) Visually examined only

B) Magnetic particle examined only

C) Liquid penetrate examined only

D) Ultrasonic shear wave examined only - ✔✔B



Which of the following is an advantage of thick film reinforced tank bottom lining?

A) easier to apply than thin film

B) initial cost is typically less than thin film

C) Provides greater resistance to moisture ingress permeation

D) Generally more accurate MFL floor scans - ✔✔C



The purpose of reviewing the welder performance qualification (WPQ) is to:

A) Verify that welder are qualified to perform the welding given its position and process

B) Verify that welds made in compliance with the WPS meet requirements

C) Verify that the welding procedure specification can produce quality welds

D) Verify that welders are qualified to perform the welding, including all essential and nonessential
variables - ✔✔A



The recommended type of internal floating roof is the:

A) Double Deck

B) Annular pontoon

C) Pan type

D) Single steel deck - ✔✔B

, API Publication 2201 on hot tapping and in-service welding covers:

A) Welding requirements

B) technical aspects

C) Inspection requirements

D) Safety aspects - ✔✔D



A repair is completed on a nozzle that was originally postweld heat treated(PWHT). It has been
determined that PWHT, of the repair, is inadvisable. Who is required to conduct a metallurgical review
prior to applying one of the alternative methods permitted in API 653?

A) A professional engineer registered in one or more states or provinces of Canada

B) A Storage tank engineer

C) The Authorized inspector responsible for the repair inspection

D) A Metallurgical engineer experienced in alternative PWHT - ✔✔B



What is another term used for "Stray currents"?

A) Short circuits

B) Positive currents

C) Impressed Currents

D) Interface currents - ✔✔D



Thick-film linings are commonly reinforced with which of the following?

A) Sand and small diameter gravel

B) Copper wire, Stainless steel wire, and low alloy steel mesh fabric

C)Chopped PVC piping, copped ABS Piping and resin beads

D) Woven glass mat, chopped glass fibers, and organic fibers - ✔✔D



How and to what extent are new welds for tank bottom plates required to be examined?

A) Newly welded bottom joints shall be tested their entire length using liquid penetrate

Geschreven voor

Vak

Documentinformatie

Geüpload op
10 juni 2024
Aantal pagina's
48
Geschreven in
2023/2024
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$9.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
hov
1.0
(2)

Ook beschikbaar in voordeelbundel

Maak kennis met de verkoper

Seller avatar
hov State University Of West Georgia
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
12
Lid sinds
2 jaar
Aantal volgers
3
Documenten
2125
Laatst verkocht
2 maanden geleden
Academic Avengers

Expert Verified Exams {Latest Versions} 99% Pass Rate

1.0

2 beoordelingen

5
0
4
0
3
0
2
0
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen