GFEBS Project Systems Course Exam With Questions And Answers What is a project definition? The project definition contains data used for the entire project. It contains default values which can be passed on to the WBS elements, or influence them, such as: Project Profile Project Control values (e.g., user status profile) Organizational data Planning parameters Settlement Rules Unique Project Number The Project Profile is often called the "DNA" of a PS project; it determines many attributes of the project. The Project Profile cannot be changed after project creation. What is a Project Definition? (2 of 2) In the project definition, default values are maintained for a project, such as the settlement rule, Person Responsible, or Plant. The default values can then be copied for a new WBS elements created for this project. The default values will be copied into new WBS elements created for the project, but may be changed with the exception of Project Profile. What is a Work Breakdown Structure? The WBS forms the basis for all subsequent planning tasks in the project. The emphasis is placed on: Planning Description Funding and Availability Control Costs and Fund Consumption Reporting Monitoring of costs, basic dates, and the statuses Work Breakdown Structure (WBS) In a WBS, the groupings of work are described in the project as individual elements in a hierarchy. The work is broken down in the project, step-by-step, until the level of detail is reached necessary to carry it out. These groupings of works are WBS Elements. So in GFEBS, a Work Breakdown Structure is a hierarchical arrangement of WBS elements under a project definition. In GFEBS, there can only be one WBS directly below the Project Definition. This is known as the Level 1 WBS, and will have the same number (and usually name) as the Project Definition. WBS Elements WBS elements are arranged hierarchically so that the most atomic work that can be described and funded with a single LOA (line of accounting) are at the bottom. Typically, execution (accrual of expenses) only occurs at this lowest level, though that does not have to be the case. Since the WBS is structured hierarchically, we're able to summarize and display the data for the corresponding higher-level WBS elements, or all the way up to the Project Definition level. Click on the note icon below for more information WBS Elements - Operative Indicators GFEBS uses Operative Indicators to define characteristics that control functionality of a WBS - they define whether a given WBS can or cannot be used in some very important processes. Click on each image for each process. Click on the note icon for more information. Planning Element WBS's that can have planned costs entered against them must be marked by checking the Planning Element operative indicator.

Show more Read less
Institution
Course

Content preview

GFEBS Project Systems Course Exam With
Questions And Answers
What is a project definition?
The project definition contains data used for the entire project. It contains default values which can
be passed on to the WBS elements, or influence them, such as:

Project Profile
Project Control values (e.g., user status profile)
Organizational data
Planning parameters
Settlement Rules
Unique Project Number

The Project Profile is often called the "DNA" of a PS project; it determines many attributes of the
project. The Project Profile cannot be changed after project creation.


What is a Project Definition? (2 of 2)
In the project definition, default values are maintained for a project, such as the settlement rule,
Person Responsible, or Plant. The default values can then be copied for a new WBS elements created
for this project.

The default values will be copied into new WBS elements created for the project, but may be changed
with the exception of Project Profile.


What is a Work Breakdown Structure?
The WBS forms the basis for all subsequent planning tasks in the project.

The emphasis is placed on:

Planning
Description
Funding and Availability Control
Costs and Fund Consumption Reporting
Monitoring of costs, basic dates, and the statuses


Work Breakdown Structure (WBS)
In a WBS, the groupings of work are described in the project as individual elements in a hierarchy. The
work is broken down in the project, step-by-step, until the level of detail is reached necessary to carry
it out. These groupings of works are WBS Elements.

So in GFEBS, a Work Breakdown Structure is a hierarchical arrangement of WBS elements under a
project definition.

In GFEBS, there can only be one WBS directly below the Project Definition. This is known as the Level
1 WBS, and will have the same number (and usually name) as the Project Definition.


WBS Elements
WBS elements are arranged hierarchically so that the most atomic work that can be described and
funded with a single LOA (line of accounting) are at the bottom. Typically, execution (accrual of
expenses) only occurs at this lowest level, though that does not have to be the case.

, Since the WBS is structured hierarchically, we're able to summarize and display the data for the
corresponding higher-level WBS elements, or all the way up to the Project Definition level.

Click on the note icon below for more information


WBS Elements - Operative Indicators
GFEBS uses Operative Indicators to define characteristics that control functionality of a WBS - they
define whether a given WBS can or cannot be used in some very important processes.

Click on each image for each process.
Click on the note icon for more information.


Planning Element
WBS's that can have planned costs entered against them must be marked by checking the Planning
Element operative indicator.


Account Assignment Element
WBS's that can have actual costs accrued (executed) against them must be marked by checking the
Account Assignment Element Operative Indicator.


Billing Element
WBS's that can be referenced on a Sales order for a reimbursable must be marked by checking the
Billing Element Operative Indicator.


Which of the following is used to define the characteristics of a WBS element?
Operative Indicators


A good project structures supports which of the following?
Cost Reporting
Funding / Funded Program Design
Execution
All of the above


True or False: In PS, the terms "Project" and "Project Definition" are synonymous
False


True or False: A WBS element can have multiple lines of accounting (LOA).
False


Project Systems Text and Documents
PS text and documents are objects that can be assigned to WBS elements. PS text are user-definable
texts that are managed in a PS text catalog. The texts are classified into different text types. You can
assign one or more WBS elements to PS text. Also, External documents in various formats (Excel,
Word, PPT, BMP, and CAD) can be assigned to WBS elements.


Project Template

Written for

Course

Document information

Uploaded on
June 22, 2024
Number of pages
14
Written in
2023/2024
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$11.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
EXAMSMART Howard Community College
Follow You need to be logged in order to follow users or courses
Sold
10
Member since
2 year
Number of followers
2
Documents
2992
Last sold
1 month ago
SMART.SCORES

On this page, you find all documents, package deals, and flashcards offered by seller LectJoshua.

5.0

2 reviews

5
2
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions