CONTAINS 4 DIFFERENT VERSIONS WITH
VERIFIED QUESTIONS AND ANSWERS
GUARANTEED PASS ALREADY GRADED A+
LATEST UPDATE
1. If a 500 kV transmission line with a surge impedance loading of 800 MW is
currently loadedat 1400 MW, which of the following events would most likely
occur?
a. Generator MVAR output would increase
b. All system capacitors would trip off-line
c. Generator MVAR output would decrease
d. All automatic reactors would connect to the system
a. Generator MVAR output would increase
2. When system conditions are such that emergency procedures are expected to
be implemented,which of the following actions should be considered first?
a. Shed firm load
b. Implement Active Load Management
c. Return outaged equipment to service
d. Request a voltage reduction
c. Return outaged equipment to service
3. If your transmission path is rated for 1200 MW and 1000 MW are scheduled
on it, but due toparallel flows the actual flow is 1300 MW, what action should
you take?
a. Request that a phase shifting transformer be installed
b. Reduce interchange transactions impacting the path
c. Request all parallel flow to PSEs to increase schedules
d. Reduce all commercial customer load
b. Reduce interchange transactions impacting the path
4. If your system is MVAR deficient, what action could be implemented to
prevent voltagecollapse?
a. Raise system frequency above 60.5 Hz
b. Shed firm load in the deficient area
c. Separate from the Interconnection
d. Lower transmission voltages
, NERC CERTIFICATION EXAM TEST BANK
CONTAINS 4 DIFFERENT VERSIONS WITH
VERIFIED QUESTIONS AND ANSWERS
GUARANTEED PASS ALREADY GRADED A+
LATEST UPDATE
b. Shed firm load in the deficient area
, NERC CERTIFICATION EXAM TEST BANK
CONTAINS 4 DIFFERENT VERSIONS WITH
VERIFIED QUESTIONS AND ANSWERS
GUARANTEED PASS ALREADY GRADED A+
LATEST UPDATE
5. Which of the following actions can a system operator take in order to maintain
stability on thesystem?
a. Request generators to absorb maximum MVAR
b. Place all operating limits on dynamic calculation
c. Raise system voltages as high as possible, but within their operating parameters
d. Reduce voltages on the transmission system
c. Raise system voltages as high as possible, but within their operating parameters
6. Which of the following actions should you take if an outage on a
neighboring system hascaused a violation on your system?
a. Open all tie-lines to your neighbor
b. Ask the Reliability Coordinator for assistance
c. Shed load to mitigate the violation
d. Wait for the neighboring system to contact you
b. Ask the Reliability Coordinator for assistance
7. If a SOL or IROL violation occurs due to transfers across the system and it is
determined thatparallel flows are contributing to the violation, what should the
system operator do?
a. Place all system capacitors in service
b. Reduce system load
c. Inform the Reliability Coordinator
d. Dump firm load
c. Inform the Reliability Coordinator
8. While performing a pre-outage study, you identify that the transmission
outage will cause a thermal violation on a parallel path, which of the following
actions would be the first one youwould implement?
a. Shed load to mitigate the concern
b. Allow the outage to occur and see what happens
c. Reschedule the outage if possible
d. Allow the outage to take place as long as no load is lost
, NERC CERTIFICATION EXAM TEST BANK
CONTAINS 4 DIFFERENT VERSIONS WITH
VERIFIED QUESTIONS AND ANSWERS
GUARANTEED PASS ALREADY GRADED A+
LATEST UPDATE
c. Reschedule the outage if possible
9. Which of the following actions should the system operator implement first if
transmission linelimits exceed the facilities emergency limits based on a
contingency that has not yet occurred, but their protocols are to respond on a
pre-contingency basis?
a. Reduce voltages in the area of the violation
b. Remove the facility from service