What are some of the outputs to the supply process? Choose three. Supply strategy, supply payment,
supply agreement, disposed system, and supply report. - ✔✔Supply strategy, supply agreement, and
supply report. 6.2.1.4
What is the Purpose of the INCOSE Systems Engineering Book? - ✔✔To define the discipline and practice
of Systems Engineering for students and practicing professionals (Section 1.1)
Systems Engineering is which of the following? Pick 3.
Profession, Skill, Methodology, Process, Perspective - ✔✔Profession, Process, Perspective (Section 2.6)
Which of the following are Agreement Processes? Select two.
Configuration management, disposal, acquisition, supply, project assessment - ✔✔Acquisition, Supply
(Section 1.3)
Define: an integrated set of activities that transforms inputs into desired outputs - ✔✔A process (Section
1.1)
#TrustIt
What is the purpose of the Tailoring process? - ✔✔Adapting processes of [ISO/IEC/IEEE 15288] to satisfy
particular circumstances or factors (Section 8.1)
Which of the following are common approaches/tips for the Tailoring process? Select four
Eliminate unnecessary outcomes, activities, tasks, and add additional ones/ Conduct tailoring at least
once for each stage/ Remove extra activities as the level of trust builds between parties/ Base decisions
, on facts and obtain approval from an independent authority/ When expertise is not available within the
organization, retain subject matter experts to provide information and specify requirements related to
agreement - ✔✔Eliminate unnecessary outcomes, Conduct tailoring once per stage, Remove extra
activities as the trust level builds, Base decisions on facts Section (8.1)
What four factors influence tailoring at the project level?
Stakeholders and customers, Project budget/schedule/requirements, Risk tolerance, Institutionalize
standards compliance at the "right"level, Complexity and precedence of the system - ✔✔Stakeholders
and customers, Project budget/schedule/requirements, Risk tolerance, complexity and precedence of
the system (Section 8.1.2)
What is Product line management (PLM)?
Bonus: What company(s) use PLM? - ✔✔PLM is a combination of product, process, management, and
organization to migrate from single-system engineering to a product line approach (Section 8.3)
What are the outputs for the configuration management process? Select three. Configuration status
accounting, configuration management strategy, configuration baselines, configuration evaluation
configuration management record - ✔✔Configuration management strategy, configuration baselines,
and configuration management record. 5.5.1.1
What is the purpose of information management? - ✔✔To maintain an archive of information produced
throughout the systems life cycle. 5.6.2.1
What are the inputs for the measurement process? Select two. Measurement needs, Measurement
strategy, Measurement Report, Measurement data - ✔✔Measurement needs and Measurement data
5.7.1.2
____________ is defined as the set of activities throughout the entire project life cycle necessary to
provide adequate confidence that a product or service conforms to stakeholder requirements or that a
process adheres to established methodology. Select one: Key Performance Parameters, Quality
Assurance, Technical Measurement Guide and Configuration Management Approach. - ✔✔Quality
Assurance. 5.8.1.1