A Subcontractor's employee incorrectly performs the Work. Who is responsible (to
the Owner) for the error?
1- Subcontractor employee
2- Architect
3- Subcontractor
4- Contractor - ANSWER A201: 3.3.2
Article 3) Contractor
3.3 Supervision and Construction Procedures
4- Contractor
Which of the following is NOT a cause for the Owner to terminate the Contract?
1- The Contractor experiences delays due to a Stop Work order through an act of
government
2- The Contractor fails to make payment to Subcontractors for labor
3- The Contractor is guilty of substantial breach of a provision of the Contract
Documents
4- The Contractor repeatedly fails to supply enough properly skilled workers -
ANSWER A201: 14.2.1
Article 14) Termination or Suspension of the Contract
14.2 Termination by the Owner for Cause
1- The Contractor experiences delays due to a Stop Work order through an act of
government
Which of the following is owner of all drawings and specifications?
1- Contractor
2- Owner
3- Architect
,4- Supplier - ANSWER A201: 1.5.1
Article 1) General Provisions
1.5 Ownership and Use of Drawings, Specifications and Other Instruments of
Service
3- Architect
Except for those Claims excluded by this AIA A201 Section 15,2,1, an initial decision
shall be required as a condition precedent to mediation of any Claim arising prior to
the date final payment is due, unless 30 days have passed after the Claim has been
referred to the Initial Decision Maker with no decision having been rendered.
1- 10
2- 20
3- 15
4- 30 - ANSWER A201: 15.2.1
Article 15) Claims and Disputes
15.2 Initial Decision
4- 30
The ____________ will on request furnish to a ____________ information regarding
percentages of completion or amounts applied for by the Contractor
1- Subcontractor; Owner
2- Architect; Subcontractor
3- Owner; Subcontractor
4- Owner; Architect - ANSWER A201: 9.6.3
Article 9) Payments and Completiong
9.6 Progress Payments
2- Architect; Subcontractor
To whom is the Subcontractor bound to by the Contract Documents?
1- Architect
2- Owner
3- Themselves
4- Contractor - ANSWER A201: 5.3
,Article 5) Subcontractors
5.3 Subcontractual Relations
4- Contractor
The Initial Decision Maker will review claims within 10 days of the receipt of the
Claim take one or more of the following actions. Which of the following actions will
NOT be taken?
1- Approve the Claim
2- Request additional supporting data from the Claimant
3- Reject the Claim
4- Ignore the request - ANSWER A201: 15.2.2
Article 15) Claims and Disputes
15.2 Initial Decision
4- Ignore the request
A Sub-subcontractor is a person or entity who has a direct or indirect contract with
a/an ________________ to perform a portion of the Work at the site
1- Contractor
2- Subcontractor
3- Architect
4- Supplier - ANSWER A201: 5.1.2
Article 5) Subcontractors
5.1 Definitions
2- Subcontractor
If the Work is stopped for a period of ______ consecutive
days through no fault of the Contractor, or Subcontractor, agents, employees or any
other persons performing portions of the Work under contract with the Contractor,
the Contractor may terminate the Contract and recover from the Owner
1- 120
2- 60
3- 30
4- 45 - ANSWER A201: 14.1.4
Article 14) Termination or Suspension of the Contract
, 14.1 Termination by the Contractor
2- 60
What is the maximum amount of time after Substantial Completion of the Work shall
all claims (by Owner and Contractor) regarding the Contract by commenced?
1- Six months
2- One year
3- Ten years
4- Five years - ANSWER A201: 13.7
Article 13: Miscellaneous Provisions
13.7 Time Limits on Claims
3- Ten years
The ____________ shall secure and pay for necessary approvals, easements,
assessments and changes required for construction
1- Owner
2- Subcontractor
3- Architect
4- Contractor - ANSWER A201: 2.2.2
Article 2) Owner
2.2 Information and Services Required of the Owner
1- Owner
The Contractor wishes to make a Claim for an increase in the Contract Sum. Written
notice as provided herein shall be given ______________.
1- Before, after, or during the execution of the Work
2- After proceeding to execute the Work
3- During the execution of the Work
4- Before proceeding to execute the Work - ANSWER A201: 15.1.4
Article 15) Claims and Disputes
15.1 Claims
15.1.4 Claims for Additional Cost