MANAGEMENT (CAPM) EXAM 2024/2025
The project manager and team should consider each process along with its inputs,
tools and outputs. As a result, they should choose which are applicable. This effort
is known as - Answer✔️✔️Tailoring
In Initiating, a project charter is created. According to the PMBOK, which person
or group may help write the charter? - Answer✔️✔️Project management team
The Monitoring and Controlling Process Group involves: - Answer✔️✔️Tracking,
reviewing, and orchestrating the progress of the project
Much information is collected and distributed during the life of the project. Data
that is collected form controlling processes and analyzed in context is called: -
Answer✔️✔️Work performance information
The project manager should perform the Initiating processes at the start of each
phase in order to: - Answer✔️✔️Keep the project focused on the business need
As Planning occurs, more and more is known about the project and the project
management plan becomes increasingly detailed. This detailing is known
specifically as: - Answer✔️✔️Progressive elaboration
The process group that involves coordinating people and resources, managing
stakeholder expectations and completing the work defined in the project
management plan is known as: - Answer✔️✔️Executing
, The Process group that contains more than 50% of the processes is known as: -
Answer✔️✔️Planning
>Direct and Manage Project Work is the process of leading and performing the
work defined in the project management plan. There are several outputs from this
process. The only one defined as typically tangible components completed to meet
the project objectives is: - Answer✔️✔️Deliverables
In conjunction with the project manager, which person or group needs to address
every process and the project environment to determine the level of
implementation for each process? - Answer✔️✔️Project team
The key benefit of one of the Integration processes is that it allows stakeholders to
understand the current state of the project, the steps taken, budget, schedule, and
scope forecasts. This process is known as: - Answer✔️✔️Monitor and Control
Project Work
The project manager should participate in the development of the project charter to
better understand the project requirements. Understanding these requirements will
better allow for: - Answer✔️✔️Efficient resource allocation to project activities
As a change control expert, you are asked to work on a plan that documents how
changes will be controlled and monitored on the project. Additionally you are told
it will ultimately become part of the project management plan. This document is
known as a: - Answer✔️✔️Change management plan
Direct and Manage Project Work requires review of all project changes and the
implementation of approved changes. This may lead to corrective action which is
defined as: - Answer✔️✔️An intentional activity that realigns the performance of
the project work with the project management plan