CAPM EXAM 2024 WITH ACCURATE ANSWERS
1. The process of establishing clear and achievable objectives, measuring their achievement, and
adjusting performance in accordance with the results of the measurement is called: -
Answer✔️✔️Management by Objectives
2. During the full life cycle of the project, a plot of the project's expected expenditures will usually follow
a characteristic S curve. This indicates that: - Answer✔️✔️The bulk of the project budget will be spent in
the execution phase
3. In which project lifecycle phase would you expect to have the greatest influence on overall project
cost? - Answer✔️✔C ️ oncept
4. Requirement is - - Answer✔️✔️Quantified and documented needs of stakeholders, customer, and
sponsor
5. TQM is - - Answer✔️✔️Total Quality Management: A common approach to implementing a quality
improvement program
6. Which describes Management Information Systems? - Answer✔️✔️Software that an enterprise uses to
support business and administrative operations
7. The type of planning that is equated with more specific data or is detailed in nature is called: -
Answer✔️✔️Tactical
8. What are the different types of costs in Microsoft Project? - Answer✔️✔️Fixed Cost, Cost Per Use,
Standard Cost, Overtime Cost
9. What is the name of PMI's Organization maturity model for project management? -
Answer✔️✔️OPM3
, 11. A group of related projects that are managed in a coordinated way that usually includes an element
of ongoing activity is called a: - Answer✔️✔️Program
12. Project constraint could be on - - Answer✔️✔️Cost, resources, schedule
13. What is true about Project Management Office (PMO)? - Answer✔️✔️Support Project Managers by
coaching and mentoring
PMO is a project stakeholder
PMO can terminate projects if required to keep business objectives consistent
14. Projects require project management while operations require business process management or
operations management. Projects can intersect with operations at various points during the product
lifecycle. Which of the following is not a stage to represent this? - Answer✔️✔️At each Executing phase
15. Enterprise environmental factors refer to both internal and external environmental factor that
surround or influence a project's success. Of the following, which is NOT an enterprise environmental
factor : - Answer✔️✔H️ istorical data
16. A person who is involved in or may be affected by the activities or anyone who has something to
gain or lose by the activity of the project is called a: - Answer✔️✔️Stakeholder
17. Large projects may be divided into smaller, more manageable components known as, -
Answer✔️✔️subprojects
18. A manager who manages a group of related projects is called a - - Answer✔️✔️Program manager
19. Which activity is conducted last as part of closing process group - Answer✔️✔️Customer satisfaction
survey
20. In the PMBOK, each process is broken into - - Answer✔️✔️Inputs and Outputs
Tools and techniques
1. The process of establishing clear and achievable objectives, measuring their achievement, and
adjusting performance in accordance with the results of the measurement is called: -
Answer✔️✔️Management by Objectives
2. During the full life cycle of the project, a plot of the project's expected expenditures will usually follow
a characteristic S curve. This indicates that: - Answer✔️✔️The bulk of the project budget will be spent in
the execution phase
3. In which project lifecycle phase would you expect to have the greatest influence on overall project
cost? - Answer✔️✔C ️ oncept
4. Requirement is - - Answer✔️✔️Quantified and documented needs of stakeholders, customer, and
sponsor
5. TQM is - - Answer✔️✔️Total Quality Management: A common approach to implementing a quality
improvement program
6. Which describes Management Information Systems? - Answer✔️✔️Software that an enterprise uses to
support business and administrative operations
7. The type of planning that is equated with more specific data or is detailed in nature is called: -
Answer✔️✔️Tactical
8. What are the different types of costs in Microsoft Project? - Answer✔️✔️Fixed Cost, Cost Per Use,
Standard Cost, Overtime Cost
9. What is the name of PMI's Organization maturity model for project management? -
Answer✔️✔️OPM3
, 11. A group of related projects that are managed in a coordinated way that usually includes an element
of ongoing activity is called a: - Answer✔️✔️Program
12. Project constraint could be on - - Answer✔️✔️Cost, resources, schedule
13. What is true about Project Management Office (PMO)? - Answer✔️✔️Support Project Managers by
coaching and mentoring
PMO is a project stakeholder
PMO can terminate projects if required to keep business objectives consistent
14. Projects require project management while operations require business process management or
operations management. Projects can intersect with operations at various points during the product
lifecycle. Which of the following is not a stage to represent this? - Answer✔️✔️At each Executing phase
15. Enterprise environmental factors refer to both internal and external environmental factor that
surround or influence a project's success. Of the following, which is NOT an enterprise environmental
factor : - Answer✔️✔H️ istorical data
16. A person who is involved in or may be affected by the activities or anyone who has something to
gain or lose by the activity of the project is called a: - Answer✔️✔️Stakeholder
17. Large projects may be divided into smaller, more manageable components known as, -
Answer✔️✔️subprojects
18. A manager who manages a group of related projects is called a - - Answer✔️✔️Program manager
19. Which activity is conducted last as part of closing process group - Answer✔️✔️Customer satisfaction
survey
20. In the PMBOK, each process is broken into - - Answer✔️✔️Inputs and Outputs
Tools and techniques