CAPM TEST PRACTICE
1. You are the project manager for the Development Corporation. You are reviewing the scope
statement for the Clinton School District Indexing System project. The Development Corporation
will provide online indexing systems for the Clinton School Library. The system is for safe
information research, retrieval and collection for the students in the Clinton School District. Your
project sponsor tells you that it's likely that the Development Corporation will identify a
consultant with a proven background in Library Science to develop the key metrics to implement
in the indexing software and to ensure correct alerts are generated when inappropriate
searching is performed. Based on the project sponsor's information, which tool will the company
rely on to assist with identifying the software program's key metrics?
The consultant's knowledge in Library Science - Answer✔️
✔️
2. The Land Development Company has plans to construct the Geneva Golf Course and Club, which
is located on a 455-acre meadow. Also, the course rests on a bluff that overlooks Lake Caroline.
Of the following, what best describes the Geneva Golf Course and Club project?
Product Scope - Answer✔️
✔️
3. of the following does the project manager and project team examine to ensure the planning of
the project's goal is achieved?
Product scope and customer expectations - Answer✔️
✔️
You are the project manager for a theme park. What should the project manager and project
team understand to create the scope statement?
The business need of the project - Answer✔️
✔️
1. A pharmacy chain wants to implement a new photo-processing option to its customers. The
option will allow customers to email, using the computer, images to the store for film processing.
However, the store chains project manager is unfamiliar with photo or film processing. What
should the project manager do?
Obtain expert judgment - Answer✔️ ✔️
2. Which of the following should every scope management plan define?
1. You are the project manager for the Development Corporation. You are reviewing the scope
statement for the Clinton School District Indexing System project. The Development Corporation
will provide online indexing systems for the Clinton School Library. The system is for safe
information research, retrieval and collection for the students in the Clinton School District. Your
project sponsor tells you that it's likely that the Development Corporation will identify a
consultant with a proven background in Library Science to develop the key metrics to implement
in the indexing software and to ensure correct alerts are generated when inappropriate
searching is performed. Based on the project sponsor's information, which tool will the company
rely on to assist with identifying the software program's key metrics?
The consultant's knowledge in Library Science - Answer✔️
✔️
2. The Land Development Company has plans to construct the Geneva Golf Course and Club, which
is located on a 455-acre meadow. Also, the course rests on a bluff that overlooks Lake Caroline.
Of the following, what best describes the Geneva Golf Course and Club project?
Product Scope - Answer✔️
✔️
3. of the following does the project manager and project team examine to ensure the planning of
the project's goal is achieved?
Product scope and customer expectations - Answer✔️
✔️
You are the project manager for a theme park. What should the project manager and project
team understand to create the scope statement?
The business need of the project - Answer✔️
✔️
1. A pharmacy chain wants to implement a new photo-processing option to its customers. The
option will allow customers to email, using the computer, images to the store for film processing.
However, the store chains project manager is unfamiliar with photo or film processing. What
should the project manager do?
Obtain expert judgment - Answer✔️ ✔️
2. Which of the following should every scope management plan define?